5420 N TAMPA AVE 91356

Certificate Information: 5420 N TAMPA AVE 91356

Application / Permit
20014-20000-04248
Plan Check / Job No.
B20VN12752
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT& ADD TO (E) DETACHED 2- CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33 (c)and (d) WITH (N) (30'-0"x 27'-0") IRR SHAPE REC ROOM AT 2ND FLOOR. WORK PER ENGINEER.
Permit Issued
Issued on 6/2/2021
Issuing Office
Current Status
CofO Issued on 2/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 TROY DEGUZMAN
Corrections Issued 10/24/2020 TROY DEGUZMAN
Quality Review Completed 10/27/2020 CHON CHIO KUO
Building Plans Picked Up 11/5/2020 APPLICANT
Plan Check Approved 6/2/2021 TROY DEGUZMAN
Issued 6/2/2021 APPLICANT
CofO in Progress 1/30/2024 SEAN HAUPT
Permit Finaled 2/6/2024 JOHN JANSON
CofO Issued 2/6/2024 JOHN JANSON
Permit Finaled 2/6/2024 JOHN JANSON

Permit Application Clearance Information

Green Code Cleared 10/23/2020 TROY DEGUZMAN
Address approval Cleared 2/2/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/2/2021 GUILLERMO PETRA
Sewer availability Cleared 2/2/2021 GUILLERMO PETRA
Low Impact Development Cleared 2/3/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 3/5/2021 GUILLERMO PETRA
Grading Pre-Inspection Cleared 3/15/2021 BRIAN MILLER
Hydrant and Access approval Cleared 6/2/2021 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh Namaghi; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/19/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 10/19/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 11/2/2021 Corrections Issued DAVID SANDOVAL
Underground Mechanical 11/5/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 11/10/2021 Corrections Issued DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 11/16/2021 Not Ready for Inspection DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 11/22/2021 Not Ready for Inspection DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 11/29/2021 Not Ready for Inspection DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 12/3/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 12/3/2021 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 12/17/2021 Partial Approval DAVID SANDOVAL
Green Building Rough 12/17/2021 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 2/8/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 2/8/2022 No Access for Inspection DAVID SANDOVAL
ELECTRICAL-Rough 3/21/2022 Partial Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 4/6/2022 Corrections Issued DAVID SANDOVAL
Green Building Rough 4/6/2022 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 4/22/2022 Not Ready for Inspection DAVID SANDOVAL
Deputy Wood Construction 5/4/2022 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 5/5/2022 Approved DAVID SANDOVAL
Green Building Rough 5/5/2022 Not Ready for Inspection DAVID SANDOVAL
Gas Test 5/10/2022 Not Ready for Inspection DAVID SANDOVAL
Green Building Rough 5/10/2022 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready DAVID SANDOVAL
BUILDING-Rough-Frame 5/13/2022 Partial Approval DAVID SANDOVAL
Green Building Rough 5/13/2022 Conditional Approval DAVID SANDOVAL
HVAC-Rough 5/13/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 5/13/2022 Partial Approval DAVID SANDOVAL
PLUMBING-Rough 5/13/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 6/6/2022 Approved ROBERT GOLD
Insulation 6/16/2022 Approved DAVID SANDOVAL
Masonry Wall/Backfill 6/16/2022 Approved DAVID SANDOVAL
Drywall Nailing 8/24/2022 Approved DAVID SANDOVAL
Green Building Rough 8/24/2022 Approved DAVID SANDOVAL
Shower Pan 10/3/2022 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 12/6/2022 Partial Approval PETER FOLLING
Masonry Wall/Backfill 12/6/2022 Not Ready for Inspection PETER FOLLING
Special/Order Compliance 12/6/2022 Partial Inspection MORRIS JACKSON
Gas Test 12/27/2022 Corrections Issued DAVID SANDOVAL
Gas Test 1/19/2023 Approved DAVID SANDOVAL
Service/Power Release 3/17/2023 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 1/23/2024 Approved SEAN HAUPT
Final 1/23/2024 Corrections Issued SEAN HAUPT
Green Building Final 1/23/2024 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Not Ready SEAN HAUPT
Smoke Detectors 1/23/2024 Approved SEAN HAUPT
Final 1/29/2024 OK to Issue CofO SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/29/2024 SGSOV Approved SEAN HAUPT