5420 N TAMPA AVE 91356
Certificate Information: 5420 N TAMPA AVE 91356
- Application / Permit
- 20014-20000-04248
- Plan Check / Job No.
- B20VN12752
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT& ADD TO (E) DETACHED 2- CAR GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33 (c)and (d) WITH (N) (30'-0"x 27'-0") IRR SHAPE REC ROOM AT 2ND FLOOR. WORK PER ENGINEER.
- Permit Issued
- Issued on 6/2/2021
- Issuing Office
- Current Status
- CofO Issued on 2/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | TROY DEGUZMAN |
| Corrections Issued | 10/24/2020 | TROY DEGUZMAN |
| Quality Review Completed | 10/27/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| Plan Check Approved | 6/2/2021 | TROY DEGUZMAN |
| Issued | 6/2/2021 | APPLICANT |
| CofO in Progress | 1/30/2024 | SEAN HAUPT |
| Permit Finaled | 2/6/2024 | JOHN JANSON |
| CofO Issued | 2/6/2024 | JOHN JANSON |
| Permit Finaled | 2/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Green Code | Cleared | 10/23/2020 | TROY DEGUZMAN |
| Address approval | Cleared | 2/2/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/2/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 2/3/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/5/2021 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 3/15/2021 | BRIAN MILLER |
| Hydrant and Access approval | Cleared | 6/2/2021 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Askarian,, Soroosh Namaghi; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 10/19/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 11/2/2021 | Corrections Issued | DAVID SANDOVAL |
| Underground Mechanical | 11/5/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 11/10/2021 | Corrections Issued | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 11/16/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 11/22/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 11/29/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 12/3/2021 | Approved | DAVID SANDOVAL |
| Footing/Foundation/Slab | 12/3/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2021 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 12/17/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 2/8/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 2/8/2022 | No Access for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 3/21/2022 | Partial Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 4/6/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 4/6/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Deputy Wood Construction | 5/4/2022 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Gas Test | 5/10/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Green Building Rough | 5/10/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Not Ready | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/13/2022 | Partial Approval | DAVID SANDOVAL |
| Green Building Rough | 5/13/2022 | Conditional Approval | DAVID SANDOVAL |
| HVAC-Rough | 5/13/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 5/13/2022 | Partial Approval | DAVID SANDOVAL |
| PLUMBING-Rough | 5/13/2022 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/6/2022 | Approved | ROBERT GOLD |
| Insulation | 6/16/2022 | Approved | DAVID SANDOVAL |
| Masonry Wall/Backfill | 6/16/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 8/24/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 8/24/2022 | Approved | DAVID SANDOVAL |
| Shower Pan | 10/3/2022 | Approved | JUSTIN HAWLEY |
| ELECTRICAL-Rough | 12/6/2022 | Partial Approval | PETER FOLLING |
| Masonry Wall/Backfill | 12/6/2022 | Not Ready for Inspection | PETER FOLLING |
| Special/Order Compliance | 12/6/2022 | Partial Inspection | MORRIS JACKSON |
| Gas Test | 12/27/2022 | Corrections Issued | DAVID SANDOVAL |
| Gas Test | 1/19/2023 | Approved | DAVID SANDOVAL |
| Service/Power Release | 3/17/2023 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 1/23/2024 | Approved | SEAN HAUPT |
| Final | 1/23/2024 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 1/23/2024 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 1/23/2024 | Approved | SEAN HAUPT |
| Final | 1/29/2024 | OK to Issue CofO | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 1/29/2024 | SGSOV Approved | SEAN HAUPT |