19050 W WELLS DR 91356
Certificate Information: 19050 W WELLS DR 91356
- Application / Permit
- 20014-20000-04215
- Plan Check / Job No.
- B20VN12665
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & ADDITION W/ATT PORCH TO (E) SFD
- Permit Issued
- Issued on 5/6/2021
- Issuing Office
- Current Status
- CofO Issued on 2/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/22/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 11/19/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/23/2020 | APPLICANT |
| Plan Check Approved | 5/5/2021 | MOHAMMAD ESMAILI |
| Issued | 5/6/2021 | APPLICANT |
| CofO in Progress | 9/12/2022 | DAVID SANDOVAL |
| Permit Finaled | 2/9/2023 | DANIEL ORRANTE |
| CofO Issued | 2/9/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/9/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 12/2/2020 | PABLO ESTRADA |
| ZA Case | Cleared | 12/2/2020 | PABLO ESTRADA |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 12/8/2020 | ABDULLAH SADOZAI |
| Distance to fire station | Cleared | 1/10/2021 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 1/10/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/12/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 3/12/2021 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 3/17/2021 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 3/17/2021 | MOHAMMAD ESMAILI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/28/2021 | Partial Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 10/12/2021 | Conditional Approval | DAVID SANDOVAL |
| Deputy Drilled-In Anchors | 10/19/2021 | Conditional Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 10/22/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 11/12/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 11/12/2021 | Corrections Issued | DAVID SANDOVAL |
| Wood Frame | 11/17/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 1/7/2022 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 1/7/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 1/7/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 1/14/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 1/14/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 2/8/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 2/22/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 2/22/2022 | Approved | DAVID SANDOVAL |
| Insulation | 2/22/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 3/3/2022 | Approved | ROBERT GOLD |
| Shower Pan | 3/3/2022 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 3/11/2022 | Approved | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2022 | Partial Inspection | JESUS PINEDA |
| Final | 8/23/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 8/23/2022 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Approved | DAVID SANDOVAL |
| Smoke Detectors | 8/23/2022 | Approved | DAVID SANDOVAL |
| Final | 9/9/2022 | OK to Issue CofO | DAVID SANDOVAL |