2157 W ADDISON WAY 90041

Certificate Information: 2157 W ADDISON WAY 90041

Application / Permit
20014-20000-04205
Plan Check / Job No.
B20VN12636
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 10' 5" X 15' 10" TO (E) GARAGE AND CONVERT TO ADU. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 5/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/20/2020 APPLICANT
Assigned to Plan Check Engineer 10/30/2020 GURUNATH NESARAJAH
Corrections Issued 10/31/2020 GURUNATH NESARAJAH
Building Plans Picked Up 11/4/2020 APPLICANT
Plan Check Approved 2/2/2021 GURUNATH NESARAJAH
Issued 2/4/2021 APPLICANT
CofO in Progress 9/25/2021 CRAIG VAUGHAN
Permit Finaled 5/21/2022 DEROLD HAUFF
CofO Issued 5/21/2022 DEROLD HAUFF
Permit Finaled 5/21/2022 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 12/10/2020 MIGUEL GAMBOA
Address approval Cleared 12/17/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 12/17/2020 CECILIO NAVARRO
Grading Pre-Inspection Cleared 1/11/2021 BRIAN MILLER
Watercourse Cleared 1/26/2021 SAM NAVID
Eng Process Fee Ord 176,300 Cleared 1/27/2021 CECILIO NAVARRO
Sewer availability Cleared 1/27/2021 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/9/2021 Corrections Issued CRAIG VAUGHAN
METHANE-Barrier 3/9/2021 Not Ready for Inspection CRAIG VAUGHAN
METHANE-Subgrade 3/9/2021 Not Ready for Inspection CRAIG VAUGHAN
Underground Mechanical 3/9/2021 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 3/12/2021 No Access for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/19/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/19/2021 Not Ready for Inspection CRAIG VAUGHAN
Sewer 3/19/2021 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 3/26/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/26/2021 Partial Approval CRAIG VAUGHAN
Sewer 3/26/2021 Approved CRAIG VAUGHAN
METHANE-Barrier 4/5/2021 Approved CRAIG VAUGHAN
METHANE-Subgrade 4/5/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 4/5/2021 Partial Approval CRAIG VAUGHAN
Footing/Foundation/Slab 4/6/2021 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/27/2021 Not Ready for Inspection CRAIG VAUGHAN
Interior/Exterior Lathing 5/7/2021 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/18/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 5/18/2021 Approved CRAIG VAUGHAN
Green Building Rough 5/18/2021 Approved CRAIG VAUGHAN
HVAC-Rough 5/18/2021 Partial Approval CRAIG VAUGHAN
METHANE-Rough 5/18/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/18/2021 Approved CRAIG VAUGHAN
Sewer 5/18/2021 Approved CRAIG VAUGHAN
Insulation 5/19/2021 Approved CRAIG VAUGHAN
Drywall Nailing 6/2/2021 Approved THOMAS LOGRASSO
PLUMBING-Rough 6/9/2021 Approved CRAIG VAUGHAN
Underground Mechanical 6/9/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Final 9/3/2021 Corrections Issued CRAIG VAUGHAN
Final 9/3/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 9/3/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Final 9/3/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 9/3/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/3/2021 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 9/3/2021 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 9/3/2021 Corrections Issued CRAIG VAUGHAN
ELECTRICAL-Final 9/24/2021 Approved CRAIG VAUGHAN
Final 9/24/2021 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 9/24/2021 Approved CRAIG VAUGHAN
HVAC-Final 9/24/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 9/24/2021 Approved CRAIG VAUGHAN
Service/Power Release 9/24/2021 Approved CRAIG VAUGHAN
Smoke Detectors 9/24/2021 Approved CRAIG VAUGHAN