6224 N ATOLL AVE 91401

Certificate Information: 6224 N ATOLL AVE 91401

Application / Permit
20014-20000-04203
Plan Check / Job No.
B20VN12633
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) FIRST FLOOR 5'-9" X 17'-7" ADDITION AND 2ND FLR ADDITION WITHIN (E) 28' X 20' GARAGE HIGH CEILING, AND CONVERT ENTIRE GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK ENGINEERING AND (E) BASEMENT TO BE BACKFILLED TO CRAWLSPACE PER PERMIT (21030-20000-03769)
Permit Issued
Issued on 6/16/2021
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/29/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/30/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 12/2/2020 OMID HEDAYAT
Building Plans Picked Up 12/3/2020 APPLICANT
Applicant returned to address corrections 4/7/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 6/14/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 6/14/2021 SEWADA ZADOORAN MILAGARDI
Issued 6/16/2021 APPLICANT
CofO in Progress 11/1/2022 CHRISTOPHE COCHRAN
CofO in Progress 11/1/2022 CHRISTOPHE COCHRAN
CofO Issued 3/4/2023 MICHAEL SMITH
Permit Finaled 3/4/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/1/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 3/1/2021 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 3/1/2021 JOHN TRIANTAFYLLOS
Sewer availability Cleared 3/1/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/4/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/8/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 2/8/2022 Corrections Issued CHRISTOPHE COCHRAN
Green Building Rough 2/8/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 2/11/2022 Approved MATT KELLERMAN
PLUMBING-Rough 2/11/2022 Approved MATT KELLERMAN
Pre-Inspection 2/11/2022 Approved MATT KELLERMAN
BUILDING-Rough-Frame 2/24/2022 Partial Approval CHRISTOPHE COCHRAN
ELECTRICAL-Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
Insulation 2/24/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 2/24/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 3/2/2022 Approved CHRISTOPHE COCHRAN
Insulation 3/2/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 3/2/2022 Partial Approval CHRISTOPHE COCHRAN
Drywall Nailing 3/4/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 3/4/2022 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 3/4/2022 Partial Approval ASHLEY THOMPSON
Final 10/17/2022 OK to Issue CofO CHRISTOPHE COCHRAN
Footing/Foundation/Slab 10/17/2022 Approved CHRISTOPHE COCHRAN
Green Building Final 10/17/2022 Approved CHRISTOPHE COCHRAN
Reinforced Concrete Frame 10/17/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 10/17/2022 Approved CHRISTOPHE COCHRAN