13268 W JUDD ST 91331
Certificate Information: 13268 W JUDD ST 91331
- Application / Permit
- 20014-20000-04193
- Plan Check / Job No.
- B20VN12606
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 26' 8" X 21' IRR.-SHAPE ADDITION TO REAR AND 18' X 18' CARPORT ADDITION TO SIDE OF (E) SFD. ALL WOR DONE PER WFPP AND LADBS INFORMATION BULLETIN.
- Permit Issued
- Issued on 10/14/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 10/1/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 8/30/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 10/6/2021 | PARISA ZAHABI |
| Plan Check Approved | 10/13/2021 | PARISA ZAHABI |
| Issued | 10/14/2021 | APPLICANT |
| Building Plans Picked Up | 10/14/2021 | APPLICANT |
| CofO in Progress | 9/27/2022 | MICHEL ABAJAN |
| CofO Issued | 9/29/2022 | MICHAEL SMITH |
| Permit Finaled | 9/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/8/2020 | LEE GUILBEAUX |
| Clean Up Green Up | Cleared | 10/27/2020 | STEVEN WECHSLER |
| Low Impact Development | Cleared | 8/19/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 8/24/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Humbert Construction Inc; Lic. No.: 415598-B | 9701 SUNLAND BLVD SHADOW HILLS, CA 91040 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/9/2021 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 12/9/2021 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 12/9/2021 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 12/9/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/23/2021 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/28/2021 | Partial Approval | MICHEL ABAJAN |
| METHANE-Rough | 12/28/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/28/2021 | Partial Approval | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 4/26/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/9/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/9/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/9/2022 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 5/9/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 5/16/2022 | Approved | MICHEL ABAJAN |
| Insulation | 5/18/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 5/18/2022 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 5/24/2022 | Approved | MICHEL ABAJAN |
| Final | 9/1/2022 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 9/1/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 9/1/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 9/27/2022 | Approved | MICHEL ABAJAN |
| Final | 9/27/2022 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 9/27/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 9/27/2022 | Approved | MICHEL ABAJAN |