6842-6844 N DELCO AVE 91306

Certificate Information: 6842-6844 N DELCO AVE 91306

Application / Permit
20014-20000-04187
Plan Check / Job No.
B20VN12582
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15'-7" X 11'-1 ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) & (e). WORK PER ENGINEER.
Permit Issued
Issued on 12/18/2020
Issuing Office
Current Status
CofO Issued on 3/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/5/2020 ROSENDO MEDINA
Corrections Issued 10/6/2020 ROSENDO MEDINA
Applicant returned to address corrections 11/23/2020 ROSENDO MEDINA
Applicant returned to address corrections 12/9/2020 ROSENDO MEDINA
Plan Check Approved 12/18/2020 ROSENDO MEDINA
Issued 12/18/2020 APPLICANT
CofO in Progress 3/16/2021 HENRY KIM
Permit Finaled 3/18/2021 JOHN JANSON
CofO Issued 3/18/2021 JOHN JANSON
Permit Finaled 3/18/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/23/2020 ABDULLAH SADOZAI
Address approval Cleared 12/15/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 12/15/2020 ABDULLAH SADOZAI
Sewer availability Cleared 12/15/2020 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,
Engineer Shakiban,, George; Lic. No.: C39908 23945 CALABASAS RD STE 101      CALABASAS, CA 91302

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/22/2020 Not Ready for Inspection BRENDAN LOONEY
Sewer 12/22/2020 Corrections Issued BRENDAN LOONEY
Underground Mechanical 12/24/2020 Partial Approval JOSEPH SAGEN
Footing/Foundation/Slab 12/30/2020 Approved HENRY KIM
PLUMBING-Rough 12/30/2020 Not Ready for Inspection HENRY KIM
Deputy Drilled-In Anchors 12/31/2020 Approved HENRY KIM
ELECTRICAL-Rough 1/5/2021 Not Ready for Inspection HENRY KIM
Sewer 1/5/2021 Corrections Issued HENRY KIM
Sewer 1/7/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/25/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 1/25/2021 Approved HENRY KIM
BUILDING-Rough-Frame 1/27/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 1/27/2021 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Approved HENRY KIM
BUILDING-Rough-Frame 1/29/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 1/29/2021 Not Ready for Inspection HENRY KIM
Green Building Rough 1/29/2021 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 2/2/2021 Not Ready for Inspection HENRY KIM
BUILDING-Rough-Frame 2/5/2021 Approved HENRY KIM
Drywall Nailing 2/5/2021 Corrections Issued HENRY KIM
ELECTRICAL-Rough 2/5/2021 Approved HENRY KIM
Green Building Rough 2/5/2021 Approved HENRY KIM
Insulation 2/5/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 2/5/2021 SGSOV Not Ready HENRY KIM
Drywall Nailing 2/9/2021 Corrections Issued HENRY KIM
Drywall Nailing 2/11/2021 Corrections Issued HENRY KIM
Drywall Nailing 2/16/2021 Approved HENRY KIM
Interior/Exterior Lathing 2/16/2021 Approved HENRY KIM
Shower Pan 2/16/2021 Corrections Issued HENRY KIM
Shower Pan 2/19/2021 Approved HENRY KIM
ELECTRICAL-Final 3/8/2021 Corrections Issued HENRY KIM
Final 3/8/2021 Corrections Issued HENRY KIM
Gas Test 3/8/2021 Corrections Issued HENRY KIM
Green Building Final 3/8/2021 Approved HENRY KIM
HVAC-Final 3/8/2021 Corrections Issued HENRY KIM
PLUMBING-Final 3/8/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/8/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 3/8/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Final 3/11/2021 Corrections Issued HENRY KIM
Final 3/11/2021 Corrections Issued HENRY KIM
HVAC-Final 3/11/2021 Approved HENRY KIM
PLUMBING-Final 3/11/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Approved HENRY KIM
Smoke Detectors 3/11/2021 Approved HENRY KIM
ELECTRICAL-Final 3/16/2021 Approved HENRY KIM
Final 3/16/2021 OK to Issue CofO HENRY KIM
Gas Test 3/16/2021 Approved HENRY KIM
Service/Power Release 3/16/2021 Approved HENRY KIM