1317 N DUENDE LANE 90272
Certificate Information: 1317 N DUENDE LANE 90272
- Application / Permit
- 20014-20000-04166
- Plan Check / Job No.
- B20VN12516
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & ADDITION TO (E) (52'-11"x 78'-8") TWO STORY SINGLE FAMILY DWELLING WITH (E) ATTACHED 2-CAR GARAGE & NEW STORAGE. NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGH OUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | TROY DEGUZMAN |
| Corrections Issued | 10/4/2020 | TROY DEGUZMAN |
| Quality Review Completed | 10/7/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/8/2020 | APPLICANT |
| Applicant returned to address corrections | 7/7/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 9/3/2021 | TROY DEGUZMAN |
| Plan Check Approved | 9/15/2021 | TROY DEGUZMAN |
| Issued | 9/15/2021 | APPLICANT |
| CofO in Progress | 11/1/2024 | EVAN COOPER |
| Permit Finaled | 11/22/2024 | RICHARD STEINBACH |
| CofO Issued | 11/22/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/22/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Coastal Zone | Cleared | 11/16/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 11/16/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 11/16/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 11/16/2020 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 11/16/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 11/16/2020 | MIGUEL GAMBOA |
| Construction near power lines | Cleared | 1/20/2021 | RIDWAN HARDY |
| BHO/Hillside ordinance | Cleared | 1/28/2021 | TRACY TATE |
| Hydrant and Access approval | Cleared | 2/16/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 4/28/2021 | ANDRES COVARRUBIAS |
| BHO/Hillside ordinance | Cleared | 5/11/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/11/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/19/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 5/19/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/19/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2021 | DINAH GARIN |
| Sewer availability | Cleared | 5/20/2021 | DINAH GARIN |
| GPI Written Notices | Cleared | 7/7/2021 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 7/7/2021 | TROY DEGUZMAN |
| Green Code | Cleared | 7/7/2021 | TROY DEGUZMAN |
Contact Information
| Architect | Mammen,, William P; Lic. No.: C8938 | 2001 LUCKY JOHN DR PARK CITY, UT 84060 |
| Contractor | Wetzel Homes Inc; Lic. No.: 1058085-B | 3531 N GALVESTON AVE SIMI VALLEY, CA 93063 |
| Engineer | Aparicio,, Daniel Gonzalo; Lic. No.: C92121 | 19332 AVENIDA DEL SOL WALNUT, CA 91789 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Geologist | Carrle,, Conrad Henry; Lic. No.: EG2359 | 23128 WILDWOOD ROAD NEWHALL, CA 91321 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/30/2021 | Corrections Issued | JOHN KIDWELL |
| Footing/Foundation/Slab | 11/30/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Special/Order Compliance | 12/1/2021 | Approved | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/8/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 12/8/2021 | Partial Approval | ANDREW NAVE |
| Deputy Drilled-In Anchors | 1/14/2022 | Conditional Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 1/21/2022 | Partial Approval | ANDREW NAVE |
| Masonry Wall/Backfill | 2/1/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 8/9/2022 | No Access for Inspection | BRENDAN LOONEY |
| PLUMBING-Rough | 8/11/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 8/24/2022 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 8/24/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 9/23/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 9/23/2022 | Corrections Issued | ANDREW NAVE |
| PLUMBING-Rough | 9/28/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 10/3/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Rough | 10/3/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Wood Construction | 10/5/2022 | Conditional Approval | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 10/7/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 10/19/2022 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 10/19/2022 | Conditional Approval | BRENDAN LOONEY |
| Green Building Rough | 10/19/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Rough-Elec/Plmb/HVAC | 10/19/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 10/19/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Deputy Wood Construction | 10/21/2022 | Conditional Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/14/2022 | Partial Approval | BRENDAN LOONEY |
| Green Building Rough | 11/14/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/14/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 11/14/2022 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | BRENDAN LOONEY |
| Insulation | 11/22/2022 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 12/13/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/30/2023 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 1/30/2023 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 2/1/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 4/4/2023 | Approved | JESUS PINEDA |
| Gas Test | 6/13/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 6/22/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Sewer | 6/22/2023 | Approved | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 12/8/2023 | Not Ready for Inspection | EVAN COOPER |
| Final | 12/8/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/8/2023 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 12/8/2023 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 12/8/2023 | Not Ready for Inspection | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/8/2023 | SGSOV Not Ready | EVAN COOPER |
| Smoke Detectors | 12/8/2023 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 12/18/2023 | Approved | EVAN COOPER |
| Final | 12/18/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 12/18/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/18/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 12/18/2023 | Not Ready for Inspection | EVAN COOPER |
| Final | 10/29/2024 | Corrections Issued | EVAN COOPER |
| Green Building Final | 10/29/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 10/29/2024 | Approved | EVAN COOPER |
| Final | 11/1/2024 | OK to Issue CofO | EVAN COOPER |