1317 N DUENDE LANE 90272

Certificate Information: 1317 N DUENDE LANE 90272

Application / Permit
20014-20000-04166
Plan Check / Job No.
B20VN12516
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO (E) (52'-11"x 78'-8") TWO STORY SINGLE FAMILY DWELLING WITH (E) ATTACHED 2-CAR GARAGE & NEW STORAGE. NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGH OUT. WORK PER ENGINEER.
Permit Issued
Issued on 9/15/2021
Issuing Office
Current Status
CofO Issued on 11/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 TROY DEGUZMAN
Corrections Issued 10/4/2020 TROY DEGUZMAN
Quality Review Completed 10/7/2020 CHON CHIO KUO
Building Plans Picked Up 10/8/2020 APPLICANT
Applicant returned to address corrections 7/7/2021 TROY DEGUZMAN
Applicant returned to address corrections 9/3/2021 TROY DEGUZMAN
Plan Check Approved 9/15/2021 TROY DEGUZMAN
Issued 9/15/2021 APPLICANT
CofO in Progress 11/1/2024 EVAN COOPER
Permit Finaled 11/22/2024 RICHARD STEINBACH
CofO Issued 11/22/2024 RICHARD STEINBACH
Permit Finaled 11/22/2024 RICHARD STEINBACH

Permit Application Clearance Information

Coastal Zone Cleared 11/16/2020 MIGUEL GAMBOA
Miscellaneous Cleared 11/16/2020 MIGUEL GAMBOA
Miscellaneous Cleared 11/16/2020 MIGUEL GAMBOA
Miscellaneous Cleared 11/16/2020 MIGUEL GAMBOA
Miscellaneous Cleared 11/16/2020 MIGUEL GAMBOA
ZA Case Cleared 11/16/2020 MIGUEL GAMBOA
Construction near power lines Cleared 1/20/2021 RIDWAN HARDY
BHO/Hillside ordinance Cleared 1/28/2021 TRACY TATE
Hydrant and Access approval Cleared 2/16/2021 MATTHEW CRAIG
Low Impact Development Cleared 4/28/2021 ANDRES COVARRUBIAS
BHO/Hillside ordinance Cleared 5/11/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 5/11/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 5/19/2021 DINAH GARIN
BHO/Hillside ordinance Cleared 5/19/2021 DINAH GARIN
Roof/Waste drainage to street Cleared 5/19/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 5/20/2021 DINAH GARIN
Sewer availability Cleared 5/20/2021 DINAH GARIN
GPI Written Notices Cleared 7/7/2021 TROY DEGUZMAN
Grading Pre-Inspection Cleared 7/7/2021 TROY DEGUZMAN
Green Code Cleared 7/7/2021 TROY DEGUZMAN

Contact Information

Architect Mammen,, William P; Lic. No.: C8938 2001 LUCKY JOHN DR      PARK CITY, UT 84060
Contractor Wetzel Homes Inc; Lic. No.: 1058085-B 3531 N GALVESTON AVE      SIMI VALLEY, CA 93063
Engineer Aparicio,, Daniel Gonzalo; Lic. No.: C92121 19332 AVENIDA DEL SOL      WALNUT, CA 91789
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Geologist Carrle,, Conrad Henry; Lic. No.: EG2359 23128 WILDWOOD ROAD      NEWHALL, CA 91321

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/30/2021 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 11/30/2021 Not Ready for Inspection JOHN KIDWELL
Special/Order Compliance 12/1/2021 Approved ANDREW NAVE
Excavation/Setback/Form/Re-Bar 12/8/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 12/8/2021 Partial Approval ANDREW NAVE
Deputy Drilled-In Anchors 1/14/2022 Conditional Approval ANDREW NAVE
Excavation/Setback/Form/Re-Bar 1/21/2022 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 1/21/2022 Partial Approval ANDREW NAVE
Masonry Wall/Backfill 2/1/2022 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 2/10/2022 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval ANDREW NAVE
PLUMBING-Rough 8/9/2022 No Access for Inspection BRENDAN LOONEY
PLUMBING-Rough 8/11/2022 Partial Approval BRENDAN LOONEY
Deputy Drilled-In Anchors 8/24/2022 Approved BRENDAN LOONEY
Footing/Foundation/Slab 8/24/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 9/23/2022 Corrections Issued ANDREW NAVE
HVAC-Rough 9/23/2022 Corrections Issued ANDREW NAVE
PLUMBING-Rough 9/28/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 10/3/2022 Corrections Issued BRENDAN LOONEY
HVAC-Rough 10/3/2022 Corrections Issued BRENDAN LOONEY
Deputy Wood Construction 10/5/2022 Conditional Approval BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 10/7/2022 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 10/19/2022 Corrections Issued BRENDAN LOONEY
Deputy Drilled-In Anchors 10/19/2022 Conditional Approval BRENDAN LOONEY
Green Building Rough 10/19/2022 Not Ready for Inspection BRENDAN LOONEY
Rough-Elec/Plmb/HVAC 10/19/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 10/19/2022 Not Ready for Inspection BRENDAN LOONEY
Deputy Wood Construction 10/21/2022 Conditional Approval BRENDAN LOONEY
BUILDING-Rough-Frame 11/14/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 11/14/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 11/14/2022 Not Ready for Inspection BRENDAN LOONEY
Verify Sprinkler Sign Off 11/14/2022 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 11/22/2022 Approved BRENDAN LOONEY
Insulation 11/22/2022 Approved BRENDAN LOONEY
Drywall Nailing 12/13/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 1/30/2023 Partial Approval BRENDAN LOONEY
Shower Pan 1/30/2023 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 2/1/2023 Partial Approval BRENDAN LOONEY
Shower Pan 2/1/2023 Approved BRENDAN LOONEY
Interior/Exterior Lathing 4/4/2023 Approved JESUS PINEDA
Gas Test 6/13/2023 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 6/22/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Sewer 6/22/2023 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 12/8/2023 Not Ready for Inspection EVAN COOPER
Final 12/8/2023 Corrections Issued EVAN COOPER
Green Building Final 12/8/2023 Not Ready for Inspection EVAN COOPER
HVAC-Final 12/8/2023 Not Ready for Inspection EVAN COOPER
PLUMBING-Final 12/8/2023 Not Ready for Inspection EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/8/2023 SGSOV Not Ready EVAN COOPER
Smoke Detectors 12/8/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 12/18/2023 Approved EVAN COOPER
Final 12/18/2023 Corrections Issued EVAN COOPER
HVAC-Final 12/18/2023 Approved EVAN COOPER
PLUMBING-Final 12/18/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Approved EVAN COOPER
Smoke Detectors 12/18/2023 Not Ready for Inspection EVAN COOPER
Final 10/29/2024 Corrections Issued EVAN COOPER
Green Building Final 10/29/2024 Approved EVAN COOPER
Smoke Detectors 10/29/2024 Approved EVAN COOPER
Final 11/1/2024 OK to Issue CofO EVAN COOPER