5946 W TUXEDO TER 90068
Certificate Information: 5946 W TUXEDO TER 90068
- Application / Permit
- 20014-20000-04131
- Plan Check / Job No.
- B20VN12451
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO (E) SFD TO CONVERT DEN TO BEDROOM, ADD (2) BATHROOMS AND 5' 1" X 3' 6" KITCHEN EXTENSION. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- Issued on 2/9/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 9/26/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/26/2021 | GURUNATH NESARAJAH |
| Issued | 2/9/2021 | APPLICANT |
Permit Application Clearance Information
| "D" conditions | Cleared | 1/14/2021 | LIKYELESH ABERA |
| CPC | Cleared | 1/14/2021 | LIKYELESH ABERA |
| Grading Pre-Inspection | Cleared | 1/26/2021 | GURUNATH NESARAJAH |
Contact Information
| Contractor | Aguilar'S Construction Inc; Lic. No.: 806448-B | 4604 WEST 129TH STREET HAWTHORNE, CA 90250 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2021 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 3/12/2021 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/21/2021 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 4/21/2021 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 4/21/2021 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 4/21/2021 | Conditional Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 4/21/2021 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 4/23/2021 | Corrections Issued | THOMAS LOGRASSO |
| Drywall Nailing | 4/27/2021 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/27/2021 | Approved | BRIAN SULLIVAN |
| Insulation | 4/27/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 4/27/2021 | Partial Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 5/4/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Reinforced Masonry Frame | 5/14/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 8/4/2021 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/20/2021 | Approved | BRIAN SULLIVAN |
| Final | 9/20/2021 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Final | 9/20/2021 | Approved | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 9/20/2021 | Approved | BRIAN SULLIVAN |
| Final | 9/23/2021 | Partial Inspection | COREY HUPP |