5946 W TUXEDO TER 90068

Certificate Information: 5946 W TUXEDO TER 90068

Application / Permit
20014-20000-04131
Plan Check / Job No.
B20VN12451
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO (E) SFD TO CONVERT DEN TO BEDROOM, ADD (2) BATHROOMS AND 5' 1" X 3' 6" KITCHEN EXTENSION. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
Issued on 2/9/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 GURUNATH NESARAJAH
Corrections Issued 9/26/2020 GURUNATH NESARAJAH
Plan Check Approved 1/26/2021 GURUNATH NESARAJAH
Issued 2/9/2021 APPLICANT

Permit Application Clearance Information

"D" conditions Cleared 1/14/2021 LIKYELESH ABERA
CPC Cleared 1/14/2021 LIKYELESH ABERA
Grading Pre-Inspection Cleared 1/26/2021 GURUNATH NESARAJAH

Contact Information

Contractor Aguilar'S Construction Inc; Lic. No.: 806448-B 4604 WEST 129TH STREET      HAWTHORNE, CA 90250

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/12/2021 Approved BRIAN SULLIVAN
Special/Order Compliance 3/12/2021 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 4/21/2021 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 4/21/2021 Approved BRIAN SULLIVAN
Green Building Rough 4/21/2021 Approved BRIAN SULLIVAN
HVAC-Rough 4/21/2021 Conditional Approval BRIAN SULLIVAN
PLUMBING-Rough 4/21/2021 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/22/2021 Not Ready for Inspection JOSEPH MCGARRY
Insulation 4/23/2021 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 4/27/2021 Approved BRIAN SULLIVAN
Footing/Foundation/Slab 4/27/2021 Approved BRIAN SULLIVAN
Insulation 4/27/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 4/27/2021 Partial Approval BRIAN SULLIVAN
Interior/Exterior Lathing 5/4/2021 Not Ready for Inspection BRIAN SULLIVAN
Reinforced Masonry Frame 5/14/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 8/4/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 9/20/2021 Approved BRIAN SULLIVAN
Final 9/20/2021 Corrections Issued BRIAN SULLIVAN
Green Building Final 9/20/2021 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Approved BRIAN SULLIVAN
Smoke Detectors 9/20/2021 Approved BRIAN SULLIVAN
Final 9/23/2021 Partial Inspection COREY HUPP