11931 W ANETA ST 90230
Certificate Information: 11931 W ANETA ST 90230
- Application / Permit
- 20014-20000-04126
- Plan Check / Job No.
- B20VN12420
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL EXT. & INT. WALLS OF (E) SINGLE FAMILY DWELLING EXCEPT FOR 20'-2" LF OF EAST SIDE AND PORTION OF FRONT WALLS OF (E) GARAGE, AND BUILD A 39'-8"x56'-6" 2-STORY SINGLE FAMILY DWELLING W/ ATT. 1-CAR GARAGE AND OPEN TRELLIS. AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- CofO Issued on 10/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | SEAN SHAHMIRI |
| Corrections Issued | 10/27/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 11/4/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/4/2020 | APPLICANT |
| Applicant returned to address corrections | 12/11/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 12/24/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/28/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/9/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 2/9/2021 | SEAN SHAHMIRI |
| Issued | 2/9/2021 | APPLICANT |
| CofO in Progress | 10/14/2021 | RICHARD STEINBACH |
| Permit Finaled | 10/20/2021 | DANIEL ORRANTE |
| CofO Issued | 10/20/2021 | DANIEL ORRANTE |
| Permit Finaled | 10/20/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2020 | TRACY TATE |
| Sewer availability | Cleared | 11/2/2020 | TRACY TATE |
| Miscellaneous | Cleared | 11/19/2020 | PEDRO AYALA |
| Low Impact Development | Cleared | 12/7/2020 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 12/8/2020 | TRACY TATE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/12/2021 | Partial Approval | DAVID HEINE |
| METHANE-Barrier | 2/12/2021 | Not Ready for Inspection | DAVID HEINE |
| METHANE-Subgrade | 2/12/2021 | Not Ready for Inspection | DAVID HEINE |
| Pool Piping | 2/12/2021 | Approved | DAVID HEINE |
| Underground Mechanical | 2/19/2021 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Partial Approval | JOHNNY MIRANDA |
| HVAC-Rough | 4/26/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/11/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/11/2021 | Corrections Issued | JOHNNY MIRANDA |
| Green Building Rough | 5/11/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| MERV13>=Rough | 5/11/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Rough | 5/11/2021 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/11/2021 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/13/2021 | Approved | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 5/13/2021 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/20/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 5/20/2021 | Approved | ENRIQUE MIRELES |
| MERV13>=Rough | 5/20/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Shower Pan | 5/20/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/27/2021 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/27/2021 | Approved | BRENDAN LOONEY |
| MERV13>=Rough | 5/27/2021 | Approved | BRENDAN LOONEY |
| Insulation | 6/2/2021 | Approved | ADAM ESCOTO |
| Drywall Nailing | 6/10/2021 | Approved | ADAM ESCOTO |
| BUILDING-Rough-Frame | 6/24/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/4/2021 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 10/4/2021 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 10/4/2021 | Conditional Approval | BRENDAN LOONEY |
| ELECTRICAL-Final | 10/7/2021 | Approved | JUAN VALENZUELA |
| Gas Test | 10/7/2021 | Approved | JUAN VALENZUELA |
| HVAC-Final | 10/7/2021 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 10/7/2021 | Approved | JUAN VALENZUELA |
| Final | 10/13/2021 | OK to Issue CofO | RICHARD STEINBACH |
| Footing/Foundation/Slab | 10/13/2021 | Approved | RICHARD STEINBACH |
| Green Building Final | 10/13/2021 | Approved | RICHARD STEINBACH |
| MERV13>=Final | 10/13/2021 | Approved | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 10/13/2021 | SGSOV Approved | RICHARD STEINBACH |
| Smoke Detectors | 10/13/2021 | Approved | RICHARD STEINBACH |