9730 W LOCKFORD ST 90035

Certificate Information: 9730 W LOCKFORD ST 90035

Application / Permit
20014-20000-04123
Plan Check / Job No.
B20VN12411
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2ND STORY ADDITION AND MAJOR REMODEL TO (E) SFD/GAR
Permit Issued
Issued on 4/29/2021
Issuing Office
Current Status
CofO Issued on 10/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 CHON CHIO KUO
Corrections Issued 9/28/2020 CHON CHIO KUO
Quality Review Completed 10/8/2020 STEVEN KIM
Building Plans Picked Up 10/9/2020 APPLICANT
Applicant returned to address corrections 4/12/2021 CHON CHIO KUO
Applicant returned to address corrections 4/13/2021 CHON CHIO KUO
Plan Check Approved 4/22/2021 CHON CHIO KUO
Issued 4/29/2021 APPLICANT
CofO in Progress 10/27/2022 DANIEL ORRANTE
Permit Finaled 10/27/2022 DANIEL ORRANTE
CofO Issued 10/27/2022 DANIEL ORRANTE
Permit Finaled 10/27/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 11/5/2020 ANTHONY MAINEZ
Hydrant and Access approval Cleared 11/17/2020 MATTHEW CRAIG
Eng Process Fee Ord 176,300 Cleared 11/18/2020 ANTHONY MAINEZ
Construction near power lines Cleared 1/29/2021 RIDWAN HARDY
Low Impact Development Cleared 4/1/2021 MITESH PATEL
Stormwater Pollution Mitigatn Cleared 4/1/2021 MITESH PATEL
GPI Written Notices Cleared 4/13/2021 CHON CHIO KUO
Grading Pre-Inspection Cleared 4/13/2021 CHON CHIO KUO
Roof/Waste drainage to street Cleared 4/15/2021 DINAH GARIN

Contact Information

Architect Samson,, Charles Andrew H; Lic. No.: C22979 6119 MARY ELLEN AVENUE      VAN NUYS, CA 91401
Contractor C R J Construction; Lic. No.: 1025947-B 23679 CALABASAS RD #973      CALABASAS, CA 91302
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/15/2021 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 6/16/2021 Partial Approval KEVIN SARGSYAN
METHANE-Barrier 6/16/2021 Approved KEVIN SARGSYAN
METHANE-Subgrade 6/16/2021 Approved KEVIN SARGSYAN
Deputy Drilled-In Anchors 6/23/2021 No Access for Inspection KEVIN SARGSYAN
Deputy Drilled-In Anchors 6/29/2021 Conditional Approval DONALD GALLAGHER
Deputy Steel/Welding 6/30/2021 No Access for Inspection DONALD GALLAGHER
Footing/Foundation/Slab 6/30/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/12/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 7/12/2021 Not Ready for Inspection KEVIN SARGSYAN
Underground Mechanical 7/12/2021 Not Ready for Inspection KEVIN SARGSYAN
Deputy Drilled-In Anchors 7/14/2021 Conditional Approval KEVIN SARGSYAN
PLUMBING-Rough 7/14/2021 Partial Approval KEVIN SARGSYAN
Underground Mechanical 7/14/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/15/2021 Partial Approval KEVIN SARGSYAN
Insulation 7/15/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/19/2021 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/20/2021 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/20/2021 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Partial Approval KEVIN SARGSYAN
Underground Mechanical 8/19/2021 No Access for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2021 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 11/8/2021 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 11/8/2021 Corrections Issued KEVIN SARGSYAN
HVAC-Rough 11/10/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 11/15/2021 Approved KEVIN SARGSYAN
HVAC-Rough 11/15/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 11/30/2021 Corrections Issued KEVIN SARGSYAN
Gas Test 11/30/2021 Partial Approval KEVIN SARGSYAN
Green Building Rough 11/30/2021 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 11/30/2021 Not Ready for Inspection KEVIN SARGSYAN
Gas Test 12/2/2021 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 12/2/2021 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 12/8/2021 Approved KEVIN SARGSYAN
Green Building Rough 12/8/2021 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/8/2021 Partial Approval KEVIN SARGSYAN
METHANE-Rough 12/8/2021 Approved KEVIN SARGSYAN
Insulation 12/23/2021 Corrections Issued KEVIN SARGSYAN
Insulation 12/28/2021 Approved KEVIN SARGSYAN
Shower Pan 1/5/2022 Approved KEVIN SARGSYAN
Drywall Nailing 1/14/2022 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 1/14/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 2/1/2022 Not Ready for Inspection KEVIN SARGSYAN
Drywall Nailing 2/10/2022 Approved EVAN COOPER
Sewer 5/17/2022 Approved KEVIN SARGSYAN
Service/Power Release 6/28/2022 Approved KENNETH NAGLE
ELECTRICAL-Final 8/24/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 8/24/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 8/26/2022 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 8/26/2022 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Final 9/1/2022 Approved OGANES TARAKHCHYAN
Gas Test 9/1/2022 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 9/1/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 9/16/2022 Corrections Issued ANDREW NAVE
Final 9/20/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Final 9/20/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 9/20/2022 SGSOV Not Ready GERMAN RODRIGUEZ MENDOZA
HVAC-Final 9/26/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/26/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 9/26/2022 Approved OGANES TARAKHCHYAN
Final 10/6/2022 Corrections Issued OGANES TARAKHCHYAN
HVAC-Final 10/6/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Not Ready OGANES TARAKHCHYAN
Final 10/11/2022 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Approved OGANES TARAKHCHYAN
Final 10/27/2022 Conditional Approval DANIEL ORRANTE