9730 W LOCKFORD ST 90035
Certificate Information: 9730 W LOCKFORD ST 90035
- Application / Permit
- 20014-20000-04123
- Plan Check / Job No.
- B20VN12411
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2ND STORY ADDITION AND MAJOR REMODEL TO (E) SFD/GAR
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- CofO Issued on 10/27/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | CHON CHIO KUO |
| Corrections Issued | 9/28/2020 | CHON CHIO KUO |
| Quality Review Completed | 10/8/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/9/2020 | APPLICANT |
| Applicant returned to address corrections | 4/12/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 4/13/2021 | CHON CHIO KUO |
| Plan Check Approved | 4/22/2021 | CHON CHIO KUO |
| Issued | 4/29/2021 | APPLICANT |
| CofO in Progress | 10/27/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/27/2022 | DANIEL ORRANTE |
| CofO Issued | 10/27/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/27/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/5/2020 | ANTHONY MAINEZ |
| Hydrant and Access approval | Cleared | 11/17/2020 | MATTHEW CRAIG |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | ANTHONY MAINEZ |
| Construction near power lines | Cleared | 1/29/2021 | RIDWAN HARDY |
| Low Impact Development | Cleared | 4/1/2021 | MITESH PATEL |
| Stormwater Pollution Mitigatn | Cleared | 4/1/2021 | MITESH PATEL |
| GPI Written Notices | Cleared | 4/13/2021 | CHON CHIO KUO |
| Grading Pre-Inspection | Cleared | 4/13/2021 | CHON CHIO KUO |
| Roof/Waste drainage to street | Cleared | 4/15/2021 | DINAH GARIN |
Contact Information
| Architect | Samson,, Charles Andrew H; Lic. No.: C22979 | 6119 MARY ELLEN AVENUE VAN NUYS, CA 91401 |
| Contractor | C R J Construction; Lic. No.: 1025947-B | 23679 CALABASAS RD #973 CALABASAS, CA 91302 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/15/2021 | Conditional Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 6/16/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Barrier | 6/16/2021 | Approved | KEVIN SARGSYAN |
| METHANE-Subgrade | 6/16/2021 | Approved | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 6/23/2021 | No Access for Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 6/29/2021 | Conditional Approval | DONALD GALLAGHER |
| Deputy Steel/Welding | 6/30/2021 | No Access for Inspection | DONALD GALLAGHER |
| Footing/Foundation/Slab | 6/30/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/12/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/12/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Underground Mechanical | 7/12/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Deputy Drilled-In Anchors | 7/14/2021 | Conditional Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/14/2021 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 7/14/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/15/2021 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 7/15/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 7/20/2021 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 8/19/2021 | No Access for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/3/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/8/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 11/8/2021 | Corrections Issued | KEVIN SARGSYAN |
| HVAC-Rough | 11/10/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/15/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 11/15/2021 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/30/2021 | Corrections Issued | KEVIN SARGSYAN |
| Gas Test | 11/30/2021 | Partial Approval | KEVIN SARGSYAN |
| Green Building Rough | 11/30/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 11/30/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Gas Test | 12/2/2021 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 12/2/2021 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 12/8/2021 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 12/8/2021 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 12/8/2021 | Partial Approval | KEVIN SARGSYAN |
| METHANE-Rough | 12/8/2021 | Approved | KEVIN SARGSYAN |
| Insulation | 12/23/2021 | Corrections Issued | KEVIN SARGSYAN |
| Insulation | 12/28/2021 | Approved | KEVIN SARGSYAN |
| Shower Pan | 1/5/2022 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 1/14/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 1/14/2022 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 2/1/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Drywall Nailing | 2/10/2022 | Approved | EVAN COOPER |
| Sewer | 5/17/2022 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 6/28/2022 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 8/24/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 8/24/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 8/26/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 8/26/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 9/1/2022 | Approved | OGANES TARAKHCHYAN |
| Gas Test | 9/1/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| PLUMBING-Final | 9/1/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 9/16/2022 | Corrections Issued | ANDREW NAVE |
| Final | 9/20/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 9/20/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Not Ready | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 9/26/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/26/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/26/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 10/6/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Final | 10/6/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 10/11/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Final | 10/27/2022 | Conditional Approval | DANIEL ORRANTE |