7766 W APPERSON ST 91042

Certificate Information: 7766 W APPERSON ST 91042

Application / Permit
20014-20000-04120
Plan Check / Job No.
B20VN12405
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
9' X 15'5"ADDITION TO THE REAR OF THE (E) SFD, AND ADD A 9' X 11'5" COVERED PATIO, ALSO AT THE REAR OF THE SFD. ALL WORK PER ENGINEER.
Permit Issued
Issued on 11/30/2020
Issuing Office
Current Status
CofO Issued on 10/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 RICHARD GARCIA
Corrections Issued 9/27/2020 RICHARD GARCIA
Plan Check Approved 11/18/2020 PINANK PATEL
Issued 11/30/2020 APPLICANT
CofO in Progress 10/15/2021 WILLIAM KUEHN
Permit Finaled 10/15/2021 MICHAEL SMITH
CofO Issued 10/15/2021 MICHAEL SMITH
Permit Finaled 10/15/2021 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/23/2020 GUILLERMO PETRA
Sewer availability Cleared 10/23/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/26/2020 GUILLERMO PETRA
Grading Pre-Inspection Cleared 10/28/2020 BARTON HOLMES

Contact Information

Contractor Owner-Builder       ,
Engineer Muradyan,, David; Lic. No.: S6232 10233 JOHANNA AVE      SUNLAND, CA 91040

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/16/2021 Partial Approval GREGG CUMMINGS
Grading Pre-Inspection 6/21/2021 Partial Inspection GREGG CUMMINGS
Deputy Drilled-In Anchors 6/22/2021 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 6/29/2021 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/14/2021 Partial Approval MATTHEW NELSON
Green Building Rough 7/14/2021 Approved MATTHEW NELSON
PLUMBING-Rough 7/14/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 8/5/2021 Not Ready for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 9/14/2021 Approved WILLIAM KUEHN
ELECTRICAL-Rough 9/14/2021 Approved WILLIAM KUEHN
Floor/Roof Diaphrgm/Shear Wall 9/14/2021 Approved WILLIAM KUEHN
HVAC-Rough 9/14/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 9/23/2021 Approved WILLIAM KUEHN
Final 10/14/2021 OK to Issue CofO WILLIAM KUEHN
Green Building Final 10/14/2021 Approved WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved WILLIAM KUEHN
Smoke Detectors 10/14/2021 Approved WILLIAM KUEHN