7717 N VARIEL AVE 91304

Certificate Information: 7717 N VARIEL AVE 91304

Application / Permit
20014-20000-04113
Plan Check / Job No.
B20VN12381
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
336 SQ. FT. ADDITION TO THE (E) SFD PER ENGINEER'S DESIGN AND DETAILS.
Permit Issued
Issued on 12/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/18/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 RICHARD GARCIA
Corrections Issued 9/27/2020 RICHARD GARCIA
Plan Check Approved 11/19/2020 OMAR GARNICA
Issued 12/14/2020 APPLICANT
CofO in Progress 10/1/2021 HENRY KIM
CofO Issued 10/7/2021 JOHN JANSON
Permit Finaled 10/7/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/15/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/16/2020 GUILLERMO PETRA
Sewer availability Cleared 10/16/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/18/2020 Approved HENRY KIM
Deputy Drilled-In Anchors 1/13/2021 Conditional Approval HENRY KIM
Deputy Wood Construction 1/13/2021 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 1/22/2021 Partial Approval HENRY KIM
ELECTRICAL-Rough 2/24/2021 Corrections Issued HENRY KIM
HVAC-Rough 2/24/2021 Corrections Issued HENRY KIM
PLUMBING-Rough 2/24/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 3/5/2021 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 3/5/2021 Approved HENRY KIM
Green Building Rough 3/5/2021 Approved HENRY KIM
HVAC-Rough 3/5/2021 Approved HENRY KIM
Interior/Exterior Lathing 3/5/2021 Approved HENRY KIM
PLUMBING-Rough 3/5/2021 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Approved HENRY KIM
Insulation 3/15/2021 Approved HENRY KIM
BUILDING-Rough-Frame 9/24/2021 Approved HENRY KIM
Drywall Nailing 9/24/2021 Approved HENRY KIM
Final 9/24/2021 Corrections Issued HENRY KIM
Green Building Final 9/24/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved HENRY KIM
Smoke Detectors 9/24/2021 Approved HENRY KIM
ELECTRICAL-Final 10/1/2021 Approved HENRY KIM
Final 10/1/2021 OK to Issue CofO HENRY KIM
HVAC-Final 10/1/2021 Approved HENRY KIM
PLUMBING-Final 10/1/2021 Approved HENRY KIM