7821 N RHODES AVE 91605

Certificate Information: 7821 N RHODES AVE 91605

Application / Permit
20014-20000-04106
Plan Check / Job No.
B20VN12362
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXTEND (E) PATIO (10'-4" X 12'-8") AT REAR OF (E) 1-STORY SFD; INTERIOR REMODEL TO (E) KITCHEN & REMOVE BEARING WALL; REPLACE (E) WINDOWS WITH SAME SIZE, TYPE & LOCATION; REPLACE HEADERS
Permit Issued
Issued on 2/24/2021
Issuing Office
Current Status
CofO Issued on 6/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 NILOOFAR MEHRAIN
Corrections Issued 11/17/2020 NILOOFAR MEHRAIN
Plan Check Approved 12/16/2020 NILOOFAR MEHRAIN
Issued 2/24/2021 APPLICANT
Building Plans Picked Up 3/3/2021 APPLICANT
CofO in Progress 4/11/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 6/20/2022 DANIEL ORRANTE
CofO Issued 6/20/2022 DANIEL ORRANTE
Permit Finaled 6/20/2022 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 11/25/2020 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 12/4/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/4/2020 ADRIAN CASTRO

Contact Information

Contractor Smart Homes Inc; Lic. No.: 1036356-B 22287 MULHOLLAND HWY #176      CALABASAS, CA 91302
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/1/2021 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 3/1/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 3/1/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 3/1/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/8/2021 Partial Approval DAVID MATSON
ELECTRICAL-Rough 3/8/2021 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 3/8/2021 Approved DAVID MATSON
PLUMBING-Rough 3/8/2021 Approved DAVID MATSON
BUILDING-Rough-Frame 3/12/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 3/12/2021 Approved JOHN HAYES
Drywall Nailing 3/17/2021 Not Ready for Inspection JOHN STEPHENS
Drywall Nailing 3/22/2021 Approved DAVID MATSON
ELECTRICAL-Final 5/10/2021 Not Ready for Inspection JOHN HAYES
Final 5/10/2021 Corrections Issued JOHN HAYES
HVAC-Final 5/10/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 5/10/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 5/10/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 8/30/2021 Not Ready for Inspection JOHN HAYES
Final 8/30/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 8/30/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 8/30/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 8/30/2021 Not Ready for Inspection JOHN HAYES
Pre-Inspection 2/16/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/11/2022 Approved CHRISTOPHER DELLEFIELD
Final 4/11/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 4/11/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/11/2022 Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 4/11/2022 Approved CHRISTOPHER DELLEFIELD