7744 N BAKMAN AVE 91352
Certificate Information: 7744 N BAKMAN AVE 91352
- Application / Permit
- 20014-20000-04105
- Plan Check / Job No.
- B20VN12360
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED GARAGE INTO ACCESSORY DWELLING UNIT WITH ADDITION PER ORD #186,481 ALL WORK PER WFPP. SEE COMMENTS.
- Permit Issued
- Issued on 1/11/2021
- Issuing Office
- Current Status
- CofO Issued on 11/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 10/4/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 10/19/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/4/2020 | HAYATO TSUCHIYA |
| No Progress | 11/19/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/19/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/11/2021 | HAYATO TSUCHIYA |
| Issued | 1/11/2021 | APPLICANT |
| CofO in Progress | 10/15/2021 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 11/1/2021 | MICHAEL SMITH |
| Permit Finaled | 11/1/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 10/6/2020 | MIGUEL GAMBOA |
| Address approval | Cleared | 10/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/9/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/9/2020 | ADRIAN CASTRO |
| Flood clearance | Cleared | 1/11/2021 | BRYAN GATHUKA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/21/2021 | Approved | JOHN HAYES |
| FLOOD-Elevation Certificate | 1/26/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 1/26/2021 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2021 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2021 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 2/26/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/9/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 3/10/2021 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 3/10/2021 | Not Ready for Inspection | JOHN HAYES |
| FLOOD-Proofing Certificate | 3/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 3/10/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 3/10/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 3/15/2021 | Approved | JOHN HAYES |
| Insulation | 3/15/2021 | Partial Approval | JOHN HAYES |
| HVAC-Rough | 3/16/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/18/2021 | Not Ready for Inspection | JOHN HAYES |
| FLOOD-Proofing Certificate | 3/18/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 3/18/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 3/18/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 3/24/2021 | Conditional Approval | DAVID MATSON |
| FLOOD-Proofing Certificate | 3/24/2021 | Approved | DAVID MATSON |
| Green Building Rough | 3/24/2021 | Not Ready for Inspection | DAVID MATSON |
| HVAC-Rough | 3/30/2021 | Approved | JOHN HAYES |
| Insulation | 3/30/2021 | Conditional Approval | JOHN HAYES |
| Insulation | 3/31/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 4/5/2021 | Not Ready for Inspection | JOHN HAYES |
| Drywall Nailing | 4/9/2021 | Approved | JOHN HAYES |
| Green Building Rough | 4/9/2021 | Approved | JOHN HAYES |
| HVAC-Rough | 4/9/2021 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 4/9/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 4/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 7/2/2021 | Corrections Issued | JOHN HAYES |
| Gas Test | 7/7/2021 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 7/23/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 7/28/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 7/28/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 7/28/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 7/28/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/18/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/18/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/18/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/18/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 8/18/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/26/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 8/26/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 8/26/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/26/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 8/26/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/3/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/3/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 9/3/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/3/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/3/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/13/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 9/13/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 9/13/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/13/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/13/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 9/17/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 9/17/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 9/17/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 9/17/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 9/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 9/17/2021 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 9/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/12/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Final | 10/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 10/12/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 10/13/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 10/15/2021 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |