17918 W LUDLOW ST 91344
Certificate Information: 17918 W LUDLOW ST 91344
- Application / Permit
- 20014-20000-04098
- Plan Check / Job No.
- B20VN12352
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (13'-8"x 39'-2") FAMILY ROOM & STUDY ROOM @ REAR AND INTERIOR REMODEL TO (E) ONE-STORY SINGLE FAMILY DWELLING. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | TROY DEGUZMAN |
| Corrections Issued | 10/17/2020 | TROY DEGUZMAN |
| Quality Review Completed | 10/19/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/21/2020 | APPLICANT |
| Applicant returned to address corrections | 1/27/2021 | TROY DEGUZMAN |
| Plan Check Approved | 2/10/2021 | TROY DEGUZMAN |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 9/9/2025 | DAVID SCANTLIN |
| Permit Finaled | 9/30/2025 | MICHAEL PELHAM |
| CofO Issued | 9/30/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/30/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Green Code | Cleared | 10/16/2020 | TROY DEGUZMAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/30/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 1/7/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/14/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | J Q S Construction Services; Lic. No.: 865672-B | 12962 FENTON AVENUE SYLMAR, CA 91342 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
| Engineer | Hernandez,, Arturo A; Lic. No.: C72517 | 8653 SHAKESPEARE LANE FRISCO, TX 75034 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/14/2021 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/23/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 8/18/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/18/2021 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 8/18/2021 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 9/10/2021 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 9/10/2021 | Approved | DAVID SCANTLIN |
| Green Building Rough | 9/10/2021 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 9/10/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 9/10/2021 | Partial Approval | DAVID SCANTLIN |
| PLUMBING-Rough | 9/10/2021 | Approved | DAVID SCANTLIN |
| Insulation | 9/28/2021 | Approved | DEANDRE HOFFMAN |
| Drywall Nailing | 10/12/2021 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 10/12/2021 | Approved | DAVID SCANTLIN |
| Shower Pan | 10/12/2021 | Approved | DAVID SCANTLIN |
| Final | 11/10/2022 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 11/10/2022 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 11/10/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 11/10/2022 | Approved | DAVID SCANTLIN |
| Final | 3/17/2025 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 3/17/2025 | SGSOV Approved | DAVID SCANTLIN |
| Final | 7/21/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 9/8/2025 | OK to Issue CofO | DAVID SCANTLIN |