24660 W OVERLAND DR 91304

Certificate Information: 24660 W OVERLAND DR 91304

Application / Permit
20014-20000-04047
Plan Check / Job No.
B20VN12269
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) DECK/PATIO. REPLACE (E) TRELLIS TO EXTEND DECK AND ADD NEW EXTERIOR STAIRS. WORK PER ENGINEER.
Permit Issued
Issued on 5/22/2021
Issuing Office
Current Status
CofO Issued on 8/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 ROSENDO MEDINA
Corrections Issued 9/26/2020 ROSENDO MEDINA
Quality Review Completed 9/29/2020 CHON CHIO KUO
Applicant returned to address corrections 1/15/2021 ROSENDO MEDINA
Applicant returned to address corrections 1/26/2021 ROSENDO MEDINA
Plan Check Approved 3/31/2021 ROSENDO MEDINA
Building Plans Picked Up 4/5/2021 APPLICANT
Issued 5/22/2021 APPLICANT
CofO in Progress 8/18/2025 JEFFREY HARTLINE
Permit Finaled 8/27/2025 JOHN JANSON
CofO Issued 8/27/2025 JOHN JANSON
Permit Finaled 8/27/2025 JOHN JANSON

Permit Application Clearance Information

ZA Case Cleared 2/4/2021 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 2/16/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 2/16/2021 GABRIEL ROBLES
GPI Written Notices Cleared 3/29/2021 ROSENDO MEDINA
Grading Pre-Inspection Cleared 3/29/2021 ROSENDO MEDINA

Contact Information

Contractor Owner-Builder       ,
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/30/2023 Partial Inspection JEFFREY HARTLINE
Pre-Inspection 1/3/2024 Partial Approval JEFFREY HARTLINE
Excavation/Setback/Form/Re-Bar 1/11/2024 Not Ready for Inspection JEFFREY HARTLINE
Footing/Foundation/Slab 1/11/2024 Not Ready for Inspection JEFFREY HARTLINE
Underground Mechanical 6/25/2024 Approved MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 7/8/2024 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 7/8/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 11/1/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/4/2024 Partial Approval JEFFREY HARTLINE
BUILDING-Rough-Frame 4/22/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 4/22/2025 Not Ready for Inspection JEFFREY HARTLINE
Final 4/22/2025 Not Ready for Inspection JEFFREY HARTLINE
PLUMBING-Final 4/22/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/22/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 4/22/2025 Approved JEFFREY HARTLINE
Final 6/20/2025 OK to Issue CofO JOHN COLEMAN