8764 N RINCON AVE 91352

Certificate Information: 8764 N RINCON AVE 91352

Application / Permit
20014-20000-04039
Plan Check / Job No.
B20VN12260
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
19'-6" X 25' IRREGULAR SHAPED ADDITION TO AND CONVERT EXISTING STORAGE AND GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) 
Permit Issued
Issued on 12/3/2020
Issuing Office
Current Status
CofO Issued on 2/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 SELLA BENYAMIN
Corrections Issued 9/29/2020 SELLA BENYAMIN
Building Plans Picked Up 10/2/2020 APPLICANT
Issued 12/3/2020 APPLICANT
CofO in Progress 1/25/2022 CHRISTOPHER DELLEFIELD
No Progress 2/5/2022 MICHAEL SMITH
CofO in Progress 2/5/2022 MICHAEL SMITH
Permit Finaled 2/5/2022 MICHAEL SMITH
CofO Issued 2/5/2022 MICHAEL SMITH
Permit Finaled 2/5/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/9/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/9/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 10/9/2020 ADRIAN CASTRO
Sewer availability Cleared 10/9/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 11/16/2020 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/23/2020 Corrections Issued JOHN HAYES
PLUMBING-Rough 12/28/2020 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 12/30/2020 Approved JOHN HAYES
BUILDING-Rough-Frame 1/21/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 1/21/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 1/21/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 1/21/2021 Approved JOHN HAYES
BUILDING-Rough-Frame 2/1/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 2/1/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 2/1/2021 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 2/1/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/9/2021 Approved JOHN HAYES
Green Building Rough 2/9/2021 Approved JOHN HAYES
MERV13>=Rough 2/9/2021 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 2/9/2021 Approved JOHN HAYES
Drywall Nailing 2/25/2021 Approved JOHN HAYES
Interior/Exterior Lathing 3/9/2021 Approved JOHN HAYES
ELECTRICAL-Final 1/6/2022 Approved CHRISTOPHER DELLEFIELD
Final 1/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 1/6/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 1/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Final 1/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 1/6/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 1/6/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 1/6/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 1/20/2022 Not Ready for Inspection JOHN HAYES
Final 1/20/2022 Corrections Issued JOHN HAYES
Green Building Final 1/20/2022 Not Ready for Inspection JOHN HAYES
HVAC-Final 1/20/2022 Not Ready for Inspection JOHN HAYES
MERV13>=Final 1/20/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 1/20/2022 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 1/25/2022 Approved CHRISTOPHER DELLEFIELD
Final 1/25/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
Green Building Final 1/25/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 1/25/2022 Approved CHRISTOPHER DELLEFIELD
MERV13>=Final 1/25/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 1/25/2022 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 1/25/2022 Approved CHRISTOPHER DELLEFIELD