5308 N LENNOX AVE 91401
Certificate Information: 5308 N LENNOX AVE 91401
- Application / Permit
- 20014-20000-04011
- Plan Check / Job No.
- B20VN12217
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE DWELLING EXCEPT FOR 6'-10" LINEAR FT OF WALL ON NORTH SIDE; ADD 34' X 59'-5" SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 1/14/2021
- Issuing Office
- Current Status
- CofO Issued on 9/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/29/2020 | SELLA BENYAMIN |
| Quality Review Completed | 10/1/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/1/2020 | APPLICANT |
| Plan Check Approved | 1/14/2021 | SELLA BENYAMIN |
| Issued | 1/14/2021 | APPLICANT |
| CofO in Progress | 8/19/2021 | MICHAEL PELHAM |
| CofO Issued | 9/2/2021 | MICHAEL SMITH |
| Permit Finaled | 9/2/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Permit | Cleared | 10/26/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/28/2020 | GUILLERMO PETRA |
| Trees in Parkway | Cleared | 11/5/2020 | JOHN KIM |
| Low Impact Development | Cleared | 12/10/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/4/2021 | Approved | ARTHUR SARGSYAN |
| Sewer | 2/4/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 2/17/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 2/24/2021 | Approved | JOHN HAYES |
| Deputy Steel/Welding | 3/4/2021 | No Access for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2021 | Partial Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2021 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/5/2021 | Corrections Issued | MICHAEL TEMPLE |
| ELECTRICAL-Rough | 4/5/2021 | Corrections Issued | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Green Building Rough | 4/5/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| HVAC-Rough | 4/5/2021 | Approved | MICHAEL TEMPLE |
| PLUMBING-Rough | 4/5/2021 | Corrections Issued | MICHAEL TEMPLE |
| Shower Pan | 4/7/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 4/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| Gas Test | 4/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 4/12/2021 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/12/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 4/16/2021 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 4/16/2021 | Partial Approval | MICHAEL TEMPLE |
| Drywall Nailing | 4/21/2021 | Approved | CHARLES POWELL |
| Drywall Nailing | 4/21/2021 | Off-Hour Fees Due | |
| ELECTRICAL-Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Final | 6/30/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| Final | 7/7/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| HVAC-Final | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Final | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/7/2021 | SGSOV Not Ready | ARTHUR SARGSYAN |
| Smoke Detectors | 7/7/2021 | No Access for Inspection | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 7/16/2021 | Approved | RICHARD DOCKUS |
| Green Building Final | 7/16/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 7/16/2021 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 7/16/2021 | Approved | RICHARD DOCKUS |
| Final | 7/20/2021 | Corrections Issued | DAVID MATSON |
| HVAC-Final | 7/20/2021 | Approved | DAVID MATSON |
| Final | 8/19/2021 | OK to Issue CofO | MICHAEL PELHAM |
| Service/Power Release | 8/19/2021 | Approved | MICHAEL PELHAM |