13416 W WEDDINGTON ST 91401
Certificate Information: 13416 W WEDDINGTON ST 91401
- Application / Permit
- 20014-20000-04010
- Plan Check / Job No.
- B20VN12208
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- APPROX 37' X 45' IRREGULAR SHAPED ADDITION AND INTERIOR REMODEL TO THE EXISING SINGLE FAMILY DWELLING; ADD 8' X 5'-7" PORCH TO THE FRONT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 1/15/2021
- Issuing Office
- Current Status
- CofO Issued on 3/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/25/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/29/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/29/2020 | APPLICANT |
| Applicant returned to address corrections | 1/7/2021 | SELLA BENYAMIN |
| Issued | 1/15/2021 | APPLICANT |
| CofO in Progress | 2/17/2022 | MISAEL ESPARZA |
| Permit Finaled | 3/1/2022 | MICHAEL SMITH |
| CofO Issued | 3/1/2022 | MICHAEL SMITH |
| Permit Finaled | 3/1/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/19/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 12/22/2020 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 12/28/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Hi-Tech Builders Inc; Lic. No.: 957111-B | 5435 BALBOA BLVD STE 200 ENCINO, CA 91316 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 2/25/2021 | Approved | ARAM AVEDISIAN |
| Wood Frame | 3/9/2021 | Corrections Issued | CHARLES POWELL |
| PLUMBING-Rough | 3/10/2021 | Partial Approval | CHARLES POWELL |
| Wood Frame | 3/10/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2021 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 5/17/2021 | Not Ready for Inspection | CHARLES POWELL |
| HVAC-Rough | 5/17/2021 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 5/17/2021 | Approved | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 5/17/2021 | Not Ready for Inspection | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 5/24/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/3/2021 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 6/3/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/9/2021 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 6/9/2021 | Not Ready for Inspection | CHARLES POWELL |
| Interior/Exterior Lathing | 6/9/2021 | Not Ready for Inspection | CHARLES POWELL |
| Wood Frame | 6/9/2021 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/16/2021 | Approved | CHARLES POWELL |
| Green Building Rough | 6/16/2021 | Not Ready for Inspection | CHARLES POWELL |
| Interior/Exterior Lathing | 6/16/2021 | Partial Approval | CHARLES POWELL |
| Insulation | 6/21/2021 | Approved | ALAN MORELOS |
| Drywall Nailing | 6/29/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/29/2021 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/4/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Gas Test | 1/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 1/4/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 1/4/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/4/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 1/4/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/3/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/3/2022 | Approved | MISAEL ESPARZA |
| Final | 2/3/2022 | Corrections Issued | MISAEL ESPARZA |
| Gas Test | 2/3/2022 | Approved | MISAEL ESPARZA |
| Green Building Final | 2/3/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 2/3/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 2/3/2022 | Approved | MISAEL ESPARZA |
| Final | 2/15/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/15/2022 | Approved | MISAEL ESPARZA |
| Final | 2/17/2022 | OK to Issue CofO | MISAEL ESPARZA |