8900-8902 N CAYUGA AVE 91352
Certificate Information: 8900-8902 N CAYUGA AVE 91352
- Application / Permit
- 20014-20000-04006
- Plan Check / Job No.
- B20VN12194
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 8'-6" x 28'-6" ADDITION TO (E) SINGLE FAMILY DWELLING TO EXTEND THE (E) BEDROOMS, AND ADD 3'-0" x 19'-6" TO AND CONVERT ATT. GARAGE TO (N) ACCEESSORY DWELLING UNIT, AND ADDITION OF NEW 20'x21' SECOND FLOOR TO ADU PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 1/17/2021
- Issuing Office
- Current Status
- CofO Issued on 3/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | SEAN SHAHMIRI |
| Corrections Issued | 10/13/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 11/6/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/6/2020 | APPLICANT |
| Applicant returned to address corrections | 12/21/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 1/13/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 1/13/2021 | SEAN SHAHMIRI |
| Issued | 1/17/2021 | APPLICANT |
| CofO in Progress | 2/22/2022 | MATT KELLERMAN |
| CofO in Progress | 2/22/2022 | MATT KELLERMAN |
| CofO Issued | 3/5/2022 | MICHAEL SMITH |
| Permit Finaled | 3/5/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/1/2020 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/4/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/5/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/3/2021 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 3/5/2021 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 3/5/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 3/18/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 4/8/2021 | Corrections Issued | JOHN HAYES |
| Drywall Nailing | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 4/8/2021 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 4/8/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 4/29/2021 | Partial Approval | JOHN HAYES |
| Green Building Rough | 4/29/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 4/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Deputy Wood Construction | 5/18/2021 | Conditional Approval | DAVID MATSON |
| Wood Frame | 5/21/2021 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 6/14/2021 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 6/14/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/14/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/28/2021 | Approved | MORRIS JACKSON |
| Wood Frame | 6/28/2021 | No Access for Inspection | JOHN HAYES |
| Wood Frame | 7/1/2021 | Corrections Issued | JOHN HAYES |
| Wood Frame | 7/8/2021 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 7/19/2021 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 7/19/2021 | Approved | MATTHEW NELSON |
| Insulation | 7/22/2021 | Partial Approval | ALAN MORELOS |
| Drywall Nailing | 7/30/2021 | Approved | WILLIAM WREN |
| Green Building Rough | 7/30/2021 | Approved | WILLIAM WREN |
| Insulation | 7/30/2021 | Approved | WILLIAM WREN |
| Shower Pan | 8/13/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 8/31/2021 | Approved | JOHN HAYES |
| Shower Pan | 8/31/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 1/10/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/10/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 1/10/2022 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 1/10/2022 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 1/10/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/10/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/10/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/18/2022 | Approved | RICHARD DOCKUS |
| Final | 1/18/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 1/18/2022 | Approved | RICHARD DOCKUS |
| MERV13>=Final | 1/18/2022 | Approved | RICHARD DOCKUS |
| MERV13>=Rough | 1/18/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 1/18/2022 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 1/18/2022 | Approved | RICHARD DOCKUS |
| Final | 2/18/2022 | OK to Issue CofO | MATT KELLERMAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2022 | SGSOV Approved | MATT KELLERMAN |
| Service/Power Release | 2/18/2022 | Approved | MATT KELLERMAN |