7406-7408 N MADORA AVE 91306
Certificate Information: 7406-7408 N MADORA AVE 91306
- Application / Permit
- 20014-20000-03990
- Plan Check / Job No.
- B20VN12134
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 24' x 29'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT (448 SQ FT) PERLAMC 12.22 A.33(c) and (e); WITH ATTACHED PATIO (220 SQ FT)
- Permit Issued
- Issued on 7/15/2021
- Issuing Office
- Current Status
- CofO Issued on 9/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | SELLA BENYAMIN |
| Corrections Issued | 9/25/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 9/28/2020 | APPLICANT |
| Plan Check Approved | 5/14/2021 | SELLA BENYAMIN |
| Issued | 7/15/2021 | APPLICANT |
| CofO in Progress | 9/23/2022 | STEVEN BACK |
| Permit Finaled | 9/29/2022 | JOHN JANSON |
| CofO Issued | 9/29/2022 | JOHN JANSON |
| Permit Finaled | 9/29/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2021 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/14/2021 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 4/29/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 6/22/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/10/2021 | Partial Approval | HENRY KIM |
| Pre-Inspection | 9/10/2021 | Partial Inspection | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 9/21/2021 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 9/22/2021 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 9/23/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 11/2/2021 | Not Ready for Inspection | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2021 | Partial Approval | STEVEN BACK |
| Green Building Rough | 11/2/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 11/19/2021 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 11/19/2021 | Approved | STEVEN BACK |
| Green Building Rough | 11/19/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 11/19/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 11/19/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 12/6/2021 | Approved | STEVEN BACK |
| Green Building Rough | 12/6/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 12/6/2021 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 12/6/2021 | Approved | STEVEN BACK |
| Sewer | 12/6/2021 | Approved | STEVEN BACK |
| Insulation | 12/15/2021 | Approved | JESUS PINEDA |
| Drywall Nailing | 12/22/2021 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 12/22/2021 | Approved | JESUS PINEDA |
| Green Building Final | 3/2/2022 | Not Ready for Inspection | STEVEN BACK |
| Final | 8/9/2022 | Corrections Issued | STEVEN BACK |
| Green Building Final | 8/9/2022 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 8/9/2022 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 8/9/2022 | Not Ready for Inspection | STEVEN BACK |
| Final | 9/23/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 9/23/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 9/23/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 9/23/2022 | Approved | STEVEN BACK |