7406-7408 N MADORA AVE 91306

Certificate Information: 7406-7408 N MADORA AVE 91306

Application / Permit
20014-20000-03990
Plan Check / Job No.
B20VN12134
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 24' x 29'-6" IRREGULAR SHAPED ACCESSORY DWELLING UNIT (448 SQ FT) PERLAMC 12.22 A.33(c) and (e); WITH ATTACHED PATIO (220 SQ FT)
Permit Issued
Issued on 7/15/2021
Issuing Office
Current Status
CofO Issued on 9/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 SELLA BENYAMIN
Corrections Issued 9/25/2020 SELLA BENYAMIN
Building Plans Picked Up 9/28/2020 APPLICANT
Plan Check Approved 5/14/2021 SELLA BENYAMIN
Issued 7/15/2021 APPLICANT
CofO in Progress 9/23/2022 STEVEN BACK
Permit Finaled 9/29/2022 JOHN JANSON
CofO Issued 9/29/2022 JOHN JANSON
Permit Finaled 9/29/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/14/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/14/2021 ADRIAN CASTRO
Sewer availability Cleared 1/14/2021 ADRIAN CASTRO
Low Impact Development Cleared 4/29/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/22/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/10/2021 Partial Approval HENRY KIM
Pre-Inspection 9/10/2021 Partial Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 9/21/2021 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 9/22/2021 Conditional Approval HENRY KIM
Footing/Foundation/Slab 9/23/2021 Approved HENRY KIM
BUILDING-Rough-Frame 11/2/2021 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Partial Approval STEVEN BACK
Green Building Rough 11/2/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 11/19/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 11/19/2021 Approved STEVEN BACK
Green Building Rough 11/19/2021 Not Ready for Inspection STEVEN BACK
HVAC-Rough 11/19/2021 Approved STEVEN BACK
PLUMBING-Rough 11/19/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 12/6/2021 Approved STEVEN BACK
Green Building Rough 12/6/2021 Approved STEVEN BACK
Interior/Exterior Lathing 12/6/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 12/6/2021 Approved STEVEN BACK
Sewer 12/6/2021 Approved STEVEN BACK
Insulation 12/15/2021 Approved JESUS PINEDA
Drywall Nailing 12/22/2021 Approved JESUS PINEDA
Interior/Exterior Lathing 12/22/2021 Approved JESUS PINEDA
Green Building Final 3/2/2022 Not Ready for Inspection STEVEN BACK
Final 8/9/2022 Corrections Issued STEVEN BACK
Green Building Final 8/9/2022 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 8/9/2022 SGSOV Not Ready STEVEN BACK
Smoke Detectors 8/9/2022 Not Ready for Inspection STEVEN BACK
Final 9/23/2022 OK to Issue CofO STEVEN BACK
Green Building Final 9/23/2022 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Approved STEVEN BACK
Smoke Detectors 9/23/2022 Approved STEVEN BACK