4116 N LAURELGROVE AVE 91604

Certificate Information: 4116 N LAURELGROVE AVE 91604

Application / Permit
20014-20000-03966
Plan Check / Job No.
B20VN12082
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 22'-5" X 24'-7" IRREGULAR SHAPED 2-STORY ADDITION TO (E) SFD. NPFA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 11/23/2020
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 RAPHAEL ROSAS
Corrections Issued 10/6/2020 RAPHAEL ROSAS
Quality Review Completed 10/6/2020 CHON CHIO KUO
Building Plans Picked Up 10/6/2020 APPLICANT
Plan Check Approved 11/23/2020 RAPHAEL ROSAS
Issued 11/23/2020 APPLICANT
CofO in Progress 8/31/2022 CHRISTOPHE COCHRAN
Permit Finaled 9/3/2022 DEROLD HAUFF
CofO Issued 9/3/2022 DEROLD HAUFF
Permit Finaled 9/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/15/2020 ADRIAN CASTRO
Sewer availability Cleared 10/15/2020 ADRIAN CASTRO
Low Impact Development Cleared 11/9/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 11/12/2020 ADRIAN CASTRO
ZI Cleared 11/19/2020 MIGUEL GAMBOA

Contact Information

Contractor M D M Custom Remodeling Inc; Lic. No.: 930166-B 5316 BABCOCK AVE      VALLEY VILLAGE, CA 91607
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/1/2020 Conditional Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 12/3/2020 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/24/2020 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 1/27/2021 Approved ARAM AVEDISIAN
Green Building Rough 1/27/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 1/27/2021 Partial Approval ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 1/27/2021 Approved ARAM AVEDISIAN
Insulation 1/29/2021 Conditional Approval MISAEL ESPARZA
Shower Pan 1/29/2021 Approved MISAEL ESPARZA
Drywall Nailing 2/4/2021 Corrections Issued BEAU COLLINS
Interior/Exterior Lathing 2/4/2021 Approved BEAU COLLINS
Drywall Nailing 2/9/2021 Approved ARAM AVEDISIAN
Insulation 2/9/2021 Approved ARAM AVEDISIAN
Service/Power Release 10/26/2021 Corrections Issued ARAM AVEDISIAN
Final 8/22/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/22/2022 Approved CHRISTOPHE COCHRAN
Green Building Final 8/22/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/22/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 8/22/2022 Approved CHRISTOPHE COCHRAN
Final 8/31/2022 OK to Issue CofO CHRISTOPHE COCHRAN