1141 S CURSON AVE 90019
Certificate Information: 1141 S CURSON AVE 90019
- Application / Permit
- 20014-20000-03949
- Plan Check / Job No.
- B20VN12006
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (34'-0"x 33'-10") IRR SHAPE @ REAR & (5'-0"x 32'-0") @ FRONT, & MAJOR REMODEL TO (E) ONE-STORY SINGLE FAMILY DWELLING WITH NFPA-13D FIRE SPRINKLER THROUGHOUT.. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/23/2021
- Issuing Office
- Current Status
- CofO Issued on 12/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | TROY DEGUZMAN |
| Corrections Issued | 10/3/2020 | TROY DEGUZMAN |
| Quality Review Completed | 10/7/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 10/8/2020 | APPLICANT |
| Plan Check Approved | 2/23/2021 | TROY DEGUZMAN |
| Issued | 2/23/2021 | APPLICANT |
| CofO in Progress | 11/24/2021 | JOSE AVILA |
| CofO in Progress | 11/24/2021 | JOSE AVILA |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
| CofO Issued | 12/3/2021 | DEROLD HAUFF |
| Permit Finaled | 12/3/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 10/13/2020 | MIGUEL GAMBOA |
| ZI | Cleared | 10/13/2020 | MIGUEL GAMBOA |
| Supp. Use District POD/CDO/TDO | Cleared | 10/15/2020 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 10/20/2020 | WALLIE JONG |
| Sewer availability | Cleared | 10/20/2020 | WALLIE JONG |
| Low Impact Development | Cleared | 12/30/2020 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 1/25/2021 | JEREMY CARTER |
Contact Information
| Contractor | Socal Construction Management Inc; Lic. No.: 984621-B | 2129 S BURNSIDE AVENUE LOS ANGELES, CA 90016 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Barrier | 3/17/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 3/17/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2021 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 4/1/2021 | Partial Approval | STUART CHAPMAN |
| METHANE-Final | 4/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 4/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 4/7/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Wood Frame | 4/7/2021 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Off-Hour Fees Due | |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 4/30/2021 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 4/30/2021 | Approved | STUART CHAPMAN |
| Sewer | 4/30/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 5/3/2021 | Approved | STUART CHAPMAN |
| HVAC-Rough | 5/3/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/4/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 5/4/2021 | Approved | STUART CHAPMAN |
| Shower Pan | 5/7/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/11/2021 | Partial Approval | WILLIAM WREN |
| Pre-Inspection | 5/11/2021 | Partial Inspection | AMY COLIN |
| Insulation | 5/17/2021 | Corrections Issued | SCOTT FINNILA |
| Special/Order Compliance | 5/17/2021 | Corrections Issued | SCOTT FINNILA |
| Interior/Exterior Lathing | 5/26/2021 | Corrections Issued | SCOTT FINNILA |
| Insulation | 6/4/2021 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/4/2021 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/9/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 6/9/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/9/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Drywall Nailing | 6/15/2021 | Approved | STUART CHAPMAN |
| Insulation | 6/15/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/15/2021 | Approved | STUART CHAPMAN |
| Gas Test | 9/29/2021 | Approved | CALEB MEISTER |
| PLUMBING-Final | 9/29/2021 | Corrections Issued | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 9/29/2021 | SGSOV Not Ready | CALEB MEISTER |
| ELECTRICAL-Final | 9/30/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 10/18/2021 | Approved | LILIANA PORTILLO |
| Green Building Final | 10/18/2021 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/18/2021 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 10/18/2021 | Approved | LILIANA PORTILLO |
| Final | 11/1/2021 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 11/1/2021 | Corrections Issued | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/1/2021 | SGSOV Approved | SCOTT FINNILA |
| Final | 11/5/2021 | Not Ready for Inspection | JOSE AVILA |
| HVAC-Final | 11/5/2021 | Corrections Issued | JOSE AVILA |
| Special/Order Compliance | 11/5/2021 | Partial Inspection | LILIANA PORTILLO |
| Final | 11/10/2021 | Conditional Approval | JOSE AVILA |
| HVAC-Final | 11/10/2021 | Approved | JOSE AVILA |
| Final | 11/19/2021 | OK to Issue CofO | JOSE AVILA |
| Final | 11/23/2021 | OK to Issue CofO | JOSE AVILA |