6315 N MORELLA AVE 91606

Certificate Information: 6315 N MORELLA AVE 91606

Application / Permit
20014-20000-03947
Plan Check / Job No.
B20VN11998
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (62'-8"x 40'-0") IRR SHAPE & MAJOR REMODEL TO (E) ONE-STORY SINGLE FAMILY DWELLING WITH NFPA-13D AUTOMATIC FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER.
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 8/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 TROY DEGUZMAN
Corrections Issued 10/3/2020 TROY DEGUZMAN
Quality Review Completed 10/5/2020 CHON CHIO KUO
Building Plans Picked Up 10/7/2020 APPLICANT
Applicant returned to address corrections 12/22/2020 TROY DEGUZMAN
Plan Check Approved 2/10/2021 PETER MOSESIAN
Issued 2/10/2021 APPLICANT
CofO in Progress 2/17/2022 JACK KARGODORIAN
Permit Finaled 8/6/2022 DEROLD HAUFF
CofO Issued 8/6/2022 DEROLD HAUFF
Permit Finaled 8/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 10/13/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/19/2020 GUILLERMO PETRA
Low Impact Development Cleared 12/8/2020 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 12/17/2020 GUILLERMO PETRA
Green Code Cleared 12/22/2020 TROY DEGUZMAN
Construction near power lines Cleared 12/29/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/17/2021 Corrections Issued DANIEL DREW
Excavation/Setback/Form/Re-Bar 3/22/2021 Approved DANIEL DREW
Underground Mechanical 3/26/2021 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Approved DANIEL DREW
HVAC-Rough 5/14/2021 Approved DANIEL DREW
PLUMBING-Rough 5/14/2021 Approved DANIEL DREW
Sewer 5/14/2021 Approved DANIEL DREW
ELECTRICAL-Rough 5/21/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 6/8/2021 Approved MISAEL ESPARZA
Green Building Rough 6/8/2021 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 6/8/2021 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 6/11/2021 Approved ALAN MORELOS
Insulation 6/21/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 6/21/2021 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 6/28/2021 Approved DANIEL DREW
Drywall Nailing 6/28/2021 Approved DANIEL DREW
Green Building Rough 6/28/2021 Approved DANIEL DREW
Interior/Exterior Lathing 7/12/2021 Approved DEANDRE HOFFMAN
Gas Test 9/9/2021 Not Ready for Inspection DANIEL DREW
Gas Test 9/13/2021 Approved DANIEL DREW
ELECTRICAL-Final 11/8/2021 Partial Inspection THOMAS FINNILA
PLUMBING-Final 11/8/2021 Partial Inspection THOMAS FINNILA
ELECTRICAL-Final 1/31/2022 Corrections Issued MISAEL ESPARZA
HVAC-Final 1/31/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 1/31/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 2/7/2022 Conditional Approval JACK KARGODORIAN
PLUMBING-Final 2/7/2022 Conditional Approval JACK KARGODORIAN
Service/Power Release 2/7/2022 Corrections Issued JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/15/2022 SGSOV Not Ready JACK KARGODORIAN
Final 2/17/2022 OK to Issue CofO JACK KARGODORIAN
Footing/Foundation/Slab 2/17/2022 Approved JACK KARGODORIAN
Green Building Final 2/17/2022 Approved JACK KARGODORIAN
HVAC-Final 2/17/2022 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Approved JACK KARGODORIAN
Service/Power Release 2/17/2022 Approved JACK KARGODORIAN
Smoke Detectors 2/17/2022 Approved JACK KARGODORIAN