11716 N GERALD AVE 91344

Certificate Information: 11716 N GERALD AVE 91344

Application / Permit
20014-20000-03917
Plan Check / Job No.
B20VN11887
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 12' X 36' PATIO COVER ADDITION TO (E) SFD PER ENGINEERING.
Permit Issued
Issued on 11/20/2020
Issuing Office
Current Status
CofO Issued on 9/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2020 APPLICANT
Assigned to Plan Check Engineer 10/2/2020 RAPHAEL ROSAS
Corrections Issued 10/5/2020 RAPHAEL ROSAS
Issued 11/20/2020 APPLICANT
CofO in Progress 3/7/2021 MARK JOHNSON
Permit Finaled 9/20/2021 MICHAEL SMITH
CofO Issued 9/20/2021 MICHAEL SMITH
Permit Finaled 9/20/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/20/2020 BARTON HOLMES
Roof/Waste drainage to street Cleared 11/5/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/12/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Lao,, Arturo Begino; Lic. No.: C56687 16348 MIDWOOD DR      GRANADA HILLS, CA 91344

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/10/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/23/2020 Partial Approval MARK JOHNSON
ELECTRICAL-Rough 12/23/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/31/2020 Approved MARK JOHNSON
Final 2/22/2021 Not Ready for Inspection MARK JOHNSON
Smoke Detectors 2/22/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Final 3/5/2021 Approved MARK JOHNSON
Final 3/5/2021 OK to Issue CofO MARK JOHNSON
HVAC-Final 3/5/2021 Approved MARK JOHNSON
PLUMBING-Final 3/5/2021 Approved MARK JOHNSON
Smoke Detectors 3/5/2021 Approved MARK JOHNSON