5117 N VARNA AVE 91423
Certificate Information: 5117 N VARNA AVE 91423
- Application / Permit
- 20014-20000-03908
- Plan Check / Job No.
- B20VN11863
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 6'-2" LF AT SOUTH SIDE AND BUILD AN IRREGULAR SHAPED 55'11" X 47' TWO STORY SINGLE FAMILLY DWELLING WITH A BALCONY AND TWO CAR GARAGE ALL WORK PER ENGINEERING NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED
- Permit Issued
- Issued on 3/8/2021
- Issuing Office
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 10/7/2020 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 10/21/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/21/2020 | APPLICANT |
| Applicant returned to address corrections | 2/16/2021 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 3/8/2021 | SEWADA ZADOORAN MILAGARDI |
| Issued | 3/8/2021 | APPLICANT |
| CofO in Progress | 11/19/2021 | MISAEL ESPARZA |
| CofO Issued | 1/29/2022 | MICHAEL SMITH |
| Permit Finaled | 1/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2020 | ADRIAN CASTRO |
| Permit | Cleared | 11/25/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/25/2020 | ADRIAN CASTRO |
| Trees in Parkway | Cleared | 12/3/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/16/2020 | MATTHEW CRAIG |
| Miscellaneous | Cleared | 1/25/2021 | PABLO ESTRADA |
| Low Impact Development | Cleared | 2/10/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 2/10/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 3/12/2021 | Partial Approval | DANIEL DREW |
| Underground Mechanical | 3/13/2021 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Approved | BEAU COLLINS |
| Footing/Foundation/Slab | 3/22/2021 | Approved | BEAU COLLINS |
| Deputy Reinf. Concrete | 3/24/2021 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 4/9/2021 | Corrections Issued | CHARLES POWELL |
| Interior/Exterior Lathing | 4/13/2021 | Partial Approval | CHARLES POWELL |
| Shower Pan | 4/13/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 4/15/2021 | Approved | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 4/15/2021 | Partial Approval | CHARLES POWELL |
| Interior/Exterior Lathing | 4/19/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 4/21/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Rough | 4/21/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 4/21/2021 | Conditional Approval | ARAM AVEDISIAN |
| Drywall Nailing | 4/29/2021 | Approved | JOHN HAYES |
| Special/Order Compliance | 4/29/2021 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 10/27/2021 | Approved | MISAEL ESPARZA |
| Final | 10/27/2021 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 10/27/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 10/27/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 10/27/2021 | Approved | MISAEL ESPARZA |
| Final | 11/9/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 11/9/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 11/9/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/19/2021 | Approved | MISAEL ESPARZA |
| Final | 11/19/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 11/19/2021 | Approved | MISAEL ESPARZA |
| HVAC-Final | 11/19/2021 | Approved | MISAEL ESPARZA |
| PLUMBING-Final | 11/19/2021 | Approved | MISAEL ESPARZA |
| Service/Power Release | 11/19/2021 | Approved | MISAEL ESPARZA |