5117 N VARNA AVE 91423

Certificate Information: 5117 N VARNA AVE 91423

Application / Permit
20014-20000-03908
Plan Check / Job No.
B20VN11863
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 6'-2" LF AT SOUTH SIDE AND BUILD AN IRREGULAR SHAPED 55'11" X 47' TWO STORY SINGLE FAMILLY DWELLING WITH A BALCONY AND TWO CAR GARAGE ALL WORK PER ENGINEERING NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED
Permit Issued
Issued on 3/8/2021
Issuing Office
Current Status
CofO Issued on 1/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/7/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 10/21/2020 STEVEN KIM
Building Plans Picked Up 10/21/2020 APPLICANT
Applicant returned to address corrections 2/16/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 3/8/2021 SEWADA ZADOORAN MILAGARDI
Issued 3/8/2021 APPLICANT
CofO in Progress 11/19/2021 MISAEL ESPARZA
CofO Issued 1/29/2022 MICHAEL SMITH
Permit Finaled 1/29/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/25/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/25/2020 ADRIAN CASTRO
Permit Cleared 11/25/2020 ADRIAN CASTRO
Sewer availability Cleared 11/25/2020 ADRIAN CASTRO
Trees in Parkway Cleared 12/3/2020 JOHN KIM
Hydrant and Access approval Cleared 12/16/2020 MATTHEW CRAIG
Miscellaneous Cleared 1/25/2021 PABLO ESTRADA
Low Impact Development Cleared 2/10/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 2/10/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 3/12/2021 Partial Approval DANIEL DREW
Underground Mechanical 3/13/2021 Off-Hour Fees Due
Excavation/Setback/Form/Re-Bar 3/22/2021 Approved BEAU COLLINS
Footing/Foundation/Slab 3/22/2021 Approved BEAU COLLINS
Deputy Reinf. Concrete 3/24/2021 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 4/5/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/7/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 4/9/2021 Corrections Issued CHARLES POWELL
Interior/Exterior Lathing 4/13/2021 Partial Approval CHARLES POWELL
Shower Pan 4/13/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 4/15/2021 Approved CHARLES POWELL
Rough-Elec/Plmb/HVAC 4/15/2021 Partial Approval CHARLES POWELL
Interior/Exterior Lathing 4/19/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 4/21/2021 Not Ready for Inspection ARAM AVEDISIAN
Green Building Rough 4/21/2021 Approved ARAM AVEDISIAN
Insulation 4/21/2021 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 4/29/2021 Approved JOHN HAYES
Special/Order Compliance 4/29/2021 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 10/27/2021 Approved MISAEL ESPARZA
Final 10/27/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 10/27/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/27/2021 SGSOV Approved MISAEL ESPARZA
Service/Power Release 10/27/2021 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 10/27/2021 Approved MISAEL ESPARZA
Final 11/9/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 11/9/2021 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 11/9/2021 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Final 11/19/2021 Approved MISAEL ESPARZA
Final 11/19/2021 OK to Issue CofO MISAEL ESPARZA
Green Building Final 11/19/2021 Approved MISAEL ESPARZA
HVAC-Final 11/19/2021 Approved MISAEL ESPARZA
PLUMBING-Final 11/19/2021 Approved MISAEL ESPARZA
Service/Power Release 11/19/2021 Approved MISAEL ESPARZA