17081 W GERMAIN ST 91344

Certificate Information: 17081 W GERMAIN ST 91344

Application / Permit
20014-20000-03894
Plan Check / Job No.
B20VN11830
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20' X 21' ADDITION FOR NEW BEDROOM AND BATHROOM TO (E) SFD. WORK PER WFPP.
Permit Issued
Issued on 10/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/18/2020 PINANK PATEL
Corrections Issued 9/21/2020 PINANK PATEL
Applicant returned to address corrections 10/6/2020 ROSENDO MEDINA
Plan Check Approved 10/8/2020 ROSENDO MEDINA
Issued 10/8/2020 APPLICANT
CofO in Progress 3/10/2021 JEFFREY PARD
Permit Finaled 3/11/2021 JOHN JANSON
CofO Issued 3/11/2021 JOHN JANSON
Permit Finaled 3/11/2021 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/29/2020 ABDULLAH SADOZAI
Roof/Waste drainage to street Cleared 9/29/2020 ABDULLAH SADOZAI
Sewer availability Cleared 9/29/2020 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/20/2020 Approved JEFFREY PARD
Footing/Foundation/Slab 10/20/2020 Not Ready for Inspection JEFFREY PARD
Pre-Inspection 10/22/2020 Approved JEFFREY PARD
Insulation 11/4/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 11/4/2020 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 11/10/2020 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 11/10/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 11/10/2020 Not Ready for Inspection JEFFREY PARD
Wood Frame 11/10/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 11/16/2020 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/20/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 11/20/2020 Corrections Issued JEFFREY PARD
Green Building Rough 11/20/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 11/20/2020 Partial Approval JEFFREY PARD
PLUMBING-Rough 11/20/2020 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 11/30/2020 Approved JEFFREY PARD
HVAC-Rough 11/30/2020 Approved JEFFREY PARD
PLUMBING-Rough 11/30/2020 Approved JEFFREY PARD
Insulation 12/4/2020 Corrections Issued JEFFREY PARD
Interior/Exterior Lathing 12/4/2020 Approved JEFFREY PARD
Wood Frame 12/4/2020 Approved JEFFREY PARD
Insulation 12/10/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 12/10/2020 Approved JEFFREY PARD
Drywall Nailing 12/17/2020 Approved JEFFREY PARD
BUILDING-Rough-Frame 3/9/2021 Approved JEFFREY PARD
Final 3/9/2021 Partial Approval JEFFREY PARD
Footing/Foundation/Slab 3/9/2021 Approved JEFFREY PARD
Green Building Final 3/9/2021 Approved JEFFREY PARD
Green Building Rough 3/9/2021 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Approved JEFFREY PARD
Smoke Detectors 3/9/2021 Approved JEFFREY PARD