17249 W LEMAY ST 91406
Certificate Information: 17249 W LEMAY ST 91406
- Application / Permit
- 20014-20000-03883
- Plan Check / Job No.
- B20VN11792
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18' X 20' DETACHED GARAGE AND ADD 15'-8" X 20' AT REAR & 17' X 13'-11" IRREGULAR SHAPED AT FRONT TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/28/2021
- Issuing Office
- Current Status
- CofO Issued on 2/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2020 | RAPHAEL ROSAS |
| Corrections Issued | 9/24/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 6/24/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 7/12/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Issued | 7/28/2021 | APPLICANT |
| CofO in Progress | 12/30/2022 | SEAN HAUPT |
| Permit Finaled | 2/3/2023 | JOHN JANSON |
| CofO Issued | 2/3/2023 | JOHN JANSON |
| Permit Finaled | 2/3/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/1/2020 | GUILLERMO PETRA |
| ZI | Cleared | 3/17/2021 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 6/11/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Urbane Builders Inc; Lic. No.: 1046293-B | 8619 RESEDA BLVD STE 304B NORTHRIDGE, CA 91324 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/15/2021 | Corrections Issued | STEVEN BACK |
| Final | 9/15/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/15/2021 | Not Ready for Inspection | STEVEN BACK |
| Pre-Inspection | 9/15/2021 | Partial Inspection | STEVEN BACK |
| PLUMBING-Rough | 9/22/2021 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 9/29/2021 | Not Ready for Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 12/2/2021 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 12/2/2021 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Rough | 2/7/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| PLUMBING-Rough | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| Wood Frame | 2/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Rough | 2/17/2022 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 2/17/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Rough | 3/22/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Rough | 3/22/2022 | Corrections Issued | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/25/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Rough | 3/25/2022 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 4/29/2022 | Corrections Issued | HENRY KIM |
| Green Building Rough | 4/29/2022 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 4/29/2022 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 6/6/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 6/6/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 6/6/2022 | Approved | SEAN HAUPT |
| Insulation | 6/23/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 7/1/2022 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 9/12/2022 | Approved | SEAN HAUPT |
| Shower Pan | 9/12/2022 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 12/27/2022 | Approved | SEAN HAUPT |
| Final | 12/27/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/27/2022 | Not Ready for Inspection | SEAN HAUPT |
| HVAC-Final | 12/27/2022 | Approved | SEAN HAUPT |
| PLUMBING-Final | 12/27/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 12/27/2022 | Not Ready for Inspection | SEAN HAUPT |
| Final | 12/29/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 12/29/2022 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 12/29/2022 | Approved | SEAN HAUPT |