328 E 73RD ST 90003

Certificate Information: 328 E 73RD ST 90003

Application / Permit
20014-20000-03881
Plan Check / Job No.
B20VN11789
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d) AND ADD FOR (3) NEW BEDROOMS & (2) NEW BATHROOMS PER ENG'R DESIGN
Permit Issued
Issued on 2/4/2021
Issuing Office
Current Status
CofO Issued on 9/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 NILOOFAR MEHRAIN
Corrections Issued 9/22/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/23/2020 APPLICANT
Plan Check Approved 1/13/2021 NILOOFAR MEHRAIN
Issued 2/4/2021 APPLICANT
CofO in Progress 9/23/2021 HORACE FULTZ
Permit Finaled 9/25/2021 DEROLD HAUFF
CofO Issued 9/25/2021 DEROLD HAUFF
Permit Finaled 9/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 10/22/2020 MATTHEW CRAIG
Community Plan Implem. Overlay Cleared 10/30/2020 ALBERT TAM
Address approval Cleared 11/2/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 11/2/2020 CECILIO NAVARRO
Low Impact Development Cleared 11/4/2020 ROBIN YAMADA
Roof/Waste drainage to street Cleared 11/4/2020 CECILIO NAVARRO
Sewer availability Cleared 11/4/2020 CECILIO NAVARRO
ZI Cleared 12/8/2020 HELEN JADALI
Construction near power lines Cleared 12/13/2020 RIDWAN HARDY
Construction within easement Cleared 12/13/2020 RIDWAN HARDY
Miscellaneous Cleared 1/16/2021 HELEN JADALI

Contact Information

Architect Gemigniani,, Richard Louis; Lic. No.: C18783 14263 VALLEY VISTA BLVD.      SHERMAN OAKS, CA 91403
Contractor Arrow Construction Co; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2021 Corrections Issued FREDDIE RIVERA
Underground Mechanical 2/10/2021 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 2/17/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 3/19/2021 Conditional Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/10/2021 Approved ROBERT CORNELL
Interior/Exterior Lathing 4/21/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 5/17/2021 Not Ready for Inspection DAVID FEILER
HVAC-Rough 5/17/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 5/17/2021 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 5/21/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/21/2021 Approved EUGENE CASSIDY
Green Building Rough 5/21/2021 Approved EUGENE CASSIDY
HVAC-Rough 5/21/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 5/21/2021 Approved EUGENE CASSIDY
Insulation 5/27/2021 Approved DAVID FEILER
Drywall Nailing 6/1/2021 Approved ANSON MAGLASANG
Shower Pan 6/22/2021 Corrections Issued DAVID FEILER
Shower Pan 6/24/2021 Corrections Issued ANSON MAGLASANG
Shower Pan 6/28/2021 Approved WILLIAM ROSE
ELECTRICAL-Final 8/10/2021 Approved JOAQUIN GREENOUGH
HVAC-Final 8/10/2021 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Final 8/10/2021 Approved JOAQUIN GREENOUGH
Final 8/18/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/18/2021 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Final 8/18/2021 Corrections Issued JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/18/2021 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 8/18/2021 Approved JOAQUIN GREENOUGH
Final 8/30/2021 OK to Issue CofO JOAQUIN GREENOUGH
Footing/Foundation/Slab 8/30/2021 Approved JOAQUIN GREENOUGH
Green Building Final 8/30/2021 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/30/2021 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 8/31/2021 Approved JOAQUIN GREENOUGH