1927 S SHERBOURNE DR 90034

Certificate Information: 1927 S SHERBOURNE DR 90034

Application / Permit
20014-20000-03861
Plan Check / Job No.
B20VN11747
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 8'-6" TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT (APPROX 440 SQ FT) PER LAMC 12.22 A.33(c) and (d); ADD 12'-7" X 13'-7" STORAGE
Permit Issued
Issued on 11/11/2020
Issuing Office
Current Status
CofO Issued on 7/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/6/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 SELLA BENYAMIN
Corrections Issued 9/21/2020 SELLA BENYAMIN
Building Plans Picked Up 9/22/2020 APPLICANT
Plan Check Approved 10/30/2020 SELLA BENYAMIN
Issued 11/11/2020 APPLICANT
CofO in Progress 7/12/2023 ARAM AVEDISIAN
Permit Finaled 7/14/2023 DANIEL ORRANTE
CofO Issued 7/14/2023 DANIEL ORRANTE
Permit Finaled 7/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/16/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/16/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/16/2020 CECILIO NAVARRO
Hydrant and Access approval Cleared 10/21/2020 KURT CORRAL
Sewer availability Cleared 10/22/2020 CECILIO NAVARRO

Contact Information

Contractor Xlart Group Inc The; Lic. No.: 791454-B 26500 AGOURA ROAD SUITE 102      CALABASAS, CA 91302

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/14/2020 Corrections Issued EVAN COOPER
Sewer 12/14/2020 Partial Approval EVAN COOPER
Underground Mechanical 12/14/2020 Partial Approval EVAN COOPER
ELECTRICAL-Rough 1/19/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Approved EVAN COOPER
PLUMBING-Rough 1/19/2021 Approved EVAN COOPER
Wood Frame 1/19/2021 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 2/8/2021 Approved EVAN COOPER
Green Building Rough 2/8/2021 Approved EVAN COOPER
HVAC-Rough 2/8/2021 Approved EVAN COOPER
Shower Pan 2/8/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 2/10/2021 Approved EVAN COOPER
Green Building Rough 2/10/2021 Approved EVAN COOPER
Insulation 2/10/2021 Approved EVAN COOPER
Interior/Exterior Lathing 2/10/2021 Partial Approval EVAN COOPER
Drywall Nailing 2/16/2021 Approved EVAN COOPER
Interior/Exterior Lathing 2/16/2021 Approved EVAN COOPER
ELECTRICAL-Final 3/17/2021 Approved EVAN COOPER
Final 3/17/2021 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 3/17/2021 Approved EVAN COOPER
Green Building Final 3/17/2021 Approved EVAN COOPER
HVAC-Final 3/17/2021 Approved EVAN COOPER
PLUMBING-Final 3/17/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 3/17/2021 Approved EVAN COOPER
Final 7/7/2023 Corrections Issued ARAM AVEDISIAN
Final 7/12/2023 OK to Issue CofO ARAM AVEDISIAN