6945 N BABCOCK AVE 91605
Certificate Information: 6945 N BABCOCK AVE 91605
- Application / Permit
- 20014-20000-03857
- Plan Check / Job No.
- B20VN11732
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ACCESSORY DWELLING UNIT ADDITION (19'8"X16'6") TO EX DETACHED GARAGE.
- Permit Issued
- Issued on 4/26/2021
- Issuing Office
- Current Status
- CofO Issued on 3/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 10/10/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 1/14/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 2/16/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 4/23/2021 | HAYATO TSUCHIYA |
| Issued | 4/26/2021 | APPLICANT |
| CofO in Progress | 3/28/2023 | MATTHEW NELSON |
| Permit Finaled | 3/28/2023 | MICHAEL SMITH |
| CofO Issued | 3/28/2023 | MICHAEL SMITH |
| Permit Finaled | 3/28/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/23/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/23/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/17/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 12/24/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rodriguez,, Jacob; Lic. No.: S5084 | 8206 ENCINO AVE NORTHRIDGE, CA 91325 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/6/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/13/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Corrections Issued | CALEB MEISTER |
| Deputy Wood Construction | 4/28/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/9/2022 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/9/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/9/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/9/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 5/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 5/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 5/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 5/26/2022 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 6/1/2022 | Approved | JACK KARGODORIAN |
| Final | 8/23/2022 | Corrections Issued | RAFAEL CORTES |
| Green Building Final | 8/23/2022 | Corrections Issued | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 8/23/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Gas Test | 9/20/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Sewer | 9/20/2022 | Approved | RAFAEL CORTES |
| Gas Test | 9/26/2022 | Approved | ALAN MORELOS |
| Sewer | 9/26/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 10/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Service/Power Release | 10/5/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Final | 10/12/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Service/Power Release | 10/12/2022 | Corrections Issued | RAFAEL CORTES |
| Underground Mechanical | 11/23/2022 | Approved | JOHN COLEMAN |
| ELECTRICAL-Final | 12/6/2022 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Final | 2/8/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 2/28/2023 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 2/28/2023 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 2/28/2023 | Corrections Issued | MATTHEW NELSON |
| Final | 3/14/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 3/14/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 3/14/2023 | Corrections Issued | KIRK SANDERS |
| Gas Test | 3/22/2023 | Corrections Issued | MATTHEW NELSON |
| Service/Power Release | 3/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 3/24/2023 | OK to Issue CofO | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 3/24/2023 | Approved | MATTHEW NELSON |