4849 N STERN AVE 91423
Certificate Information: 4849 N STERN AVE 91423
- Application / Permit
- 20014-20000-03834
- Plan Check / Job No.
- B20VN11624
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 43'-1" x 34'-9" IRREGULAR SHAPE ADDITION & REMODEL TO (E) SINGLE FAMILY DWELLING. AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/2/2020 | SEAN SHAHMIRI |
| Corrections Issued | 10/6/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 10/30/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/2/2020 | APPLICANT |
| Plan Check Approved | 4/16/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 4/19/2021 | SEAN SHAHMIRI |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 8/16/2022 | MISAEL ESPARZA |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
| CofO Issued | 8/16/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/16/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZI | Cleared | 12/16/2020 | RUBEN VASQUEZ |
| Sewer availability | Cleared | 12/30/2020 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 1/4/2021 | ABDULLAH SADOZAI |
| Low Impact Development | Cleared | 2/25/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/23/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Aguirre Rosales Construction Inc; Lic. No.: 1039164-B | 19055 PARTHENIA STREET NORTHRIDGE, CA 91324 |
| Engineer | Babapirzadeh,, Ghazal; Lic. No.: C90480 | 1530 N DETROIT ST APT 109 LOS ANGELES, CA 90046 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/20/2021 | Conditional Approval | MORRIS JACKSON |
| Excavation/Setback/Form/Re-Bar | 5/21/2021 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 6/15/2021 | Corrections Issued | CHARLES POWELL |
| PLUMBING-Rough | 6/21/2021 | Partial Approval | ARAM AVEDISIAN |
| Deputy Wood Construction | 8/4/2021 | Corrections Issued | CHARLES POWELL |
| ELECTRICAL-Rough | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 8/6/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/17/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 8/17/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 8/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 8/17/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 9/1/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 9/1/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 9/1/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/8/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/8/2021 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/8/2021 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 9/8/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/8/2021 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 9/8/2021 | Approved | ARAM AVEDISIAN |
| Insulation | 9/15/2021 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 9/17/2021 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 9/21/2021 | Corrections Issued | MISAEL ESPARZA |
| Drywall Nailing | 9/24/2021 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 9/24/2021 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 9/28/2021 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 1/10/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 1/10/2022 | Approved | MISAEL ESPARZA |
| Green Building Final | 1/10/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2022 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 1/10/2022 | Approved | MISAEL ESPARZA |
| Final | 1/25/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 1/25/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 2/17/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 2/17/2022 | Approved | MISAEL ESPARZA |
| Final | 8/8/2022 | No Access for Inspection | MISAEL ESPARZA |
| Final | 8/15/2022 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 8/15/2022 | Approved | MISAEL ESPARZA |