22136 W AVENUE MORELOS 91364

Certificate Information: 22136 W AVENUE MORELOS 91364

Application / Permit
20014-20000-03829
Plan Check / Job No.
B20VN11617
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 22' X 20" ATTACHED CARPORT TO HABITABLE SPACE, ADD 20' X 7' IRR.-SHAPE PORCHES TO FRONT, 22' 2" X 7' 6" HABITABLE SPACE ADDITION TO REAR AND ADD (2) 18' X 9' CARPORTS TO FRONT OF (E) SFD.
Permit Issued
Issued on 1/27/2022
Issuing Office
Current Status
CofO Issued on 1/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 GURUNATH NESARAJAH
Corrections Issued 9/29/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 2/10/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 8/13/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 11/5/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 12/3/2021 GURUNATH NESARAJAH
Applicant returned to address corrections 1/19/2022 SAMUEL GONZALEZ
Plan Check Approved 1/25/2022 SAMUEL GONZALEZ
Issued 1/27/2022 APPLICANT
Building Plans Picked Up 1/31/2022 APPLICANT
CofO in Progress 10/5/2022 JOHN KIDWELL
CofO Issued 1/27/2023 JOHN JANSON
Permit Finaled 1/27/2023 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/20/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 10/20/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 10/20/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 10/20/2020 ADRIAN CASTRO
BHO/Hillside ordinance Cleared 10/20/2020 ADRIAN CASTRO
Sewer availability Cleared 10/20/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 11/10/2020 BRIAN MILLER
Eng Process Fee Ord 176,300 Cleared 12/22/2020 ADRIAN CASTRO
Low Impact Development Cleared 1/26/2021 MITESH PATEL
GPI Written Notices Cleared 2/10/2021 GURUNATH NESARAJAH
Roof/Waste drainage to street Cleared 2/23/2021 GUILLERMO PETRA
Specific Plan Cleared 7/22/2021 OLGA AYALA

Contact Information

Architect Koch,, Richard W; Lic. No.: C13782 5920 PALOMAR CIRCLE      CAMARILLO, CA 930127131
Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Rough 2/24/2022 Partial Approval PETER FOLLING
Sewer 2/24/2022 Approved PETER FOLLING
Deputy Drilled-In Anchors 3/1/2022 Conditional Approval JESUS PINEDA
Footing/Foundation/Slab 3/3/2022 Partial Approval PETER FOLLING
Excavation/Setback/Form/Re-Bar 3/11/2022 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 3/24/2022 Partial Approval PETER FOLLING
Green Building Rough 3/24/2022 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval PETER FOLLING
Footing/Foundation/Slab 4/22/2022 Approved PETER FOLLING
Green Building Rough 4/22/2022 Not Ready for Inspection PETER FOLLING
BUILDING-Rough-Frame 5/31/2022 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 5/31/2022 Approved MORRIS JACKSON
Green Building Rough 5/31/2022 Not Ready for Inspection MORRIS JACKSON
PLUMBING-Rough 5/31/2022 Approved MORRIS JACKSON
Wood Frame 5/31/2022 Approved MORRIS JACKSON
ELECTRICAL-Rough 6/17/2022 Approved VINCENT HANLEY
HVAC-Rough 6/17/2022 Approved VINCENT HANLEY
Insulation 6/17/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/17/2022 Approved VINCENT HANLEY
Drywall Nailing 7/11/2022 Approved PETER FOLLING
Interior/Exterior Lathing 7/15/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 9/28/2022 Approved PETER FOLLING
ELECTRICAL-Final 9/28/2022 Not Ready for Inspection PETER FOLLING
Final 9/28/2022 Corrections Issued PETER FOLLING
Green Building Final 9/28/2022 Not Ready for Inspection PETER FOLLING
Green Building Rough 9/28/2022 Approved PETER FOLLING
HVAC-Final 9/28/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Final 9/28/2022 Not Ready for Inspection PETER FOLLING
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Not Ready PETER FOLLING
Smoke Detectors 9/28/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Final 10/4/2022 Approved JOHN KIDWELL
Grounding or Bonding 10/4/2022 Approved JOHN KIDWELL
HVAC-Final 10/4/2022 Approved JOHN KIDWELL
PLUMBING-Final 10/4/2022 Approved JOHN KIDWELL
Service/Power Release 10/4/2022 Partial Inspection JOHN KIDWELL
Final 10/5/2022 OK to Issue CofO JOHN KIDWELL
Green Building Final 10/5/2022 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved JOHN KIDWELL
Smoke Detectors 10/5/2022 Approved JOHN KIDWELL