8353 S GEORGETOWN AVE 90045
Certificate Information: 8353 S GEORGETOWN AVE 90045
- Application / Permit
- 20014-20000-03824
- Plan Check / Job No.
- B20VN11611
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 14'-5" X 20'-5" TO EXTEND (E) BEDROOM/BATHROOM/CLOSET. ALL WORK PER WFPP.
- Permit Issued
- Issued on 11/2/2020
- Issuing Office
- Current Status
- CofO Issued on 9/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | CRISTINA SALAZAR |
| Corrections Issued | 9/10/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 10/5/2020 | JENNIFER LEE |
| Plan Check Approved | 10/29/2020 | JENNIFER LEE |
| Issued | 11/2/2020 | APPLICANT |
| CofO in Progress | 8/17/2021 | BRENDAN LOONEY |
| Permit Finaled | 9/25/2021 | DANIEL ORRANTE |
| Permit Finaled | 9/25/2021 | DANIEL ORRANTE |
| CofO Issued | 9/25/2021 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2020 | DINAH GARIN |
| Specific Plan | Cleared | 10/19/2020 | PEDRO AYALA |
| Specific Plan | Cleared | 10/22/2020 | MIGUEL GAMBOA |
| Roof/Waste drainage to street | Cleared | 10/30/2020 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/1/2021 | Corrections Issued | DAVID HEINE |
| Piling/Pier/Caisson | 3/1/2021 | Not Ready for Inspection | DAVID HEINE |
| Deputy Drilled-In Anchors | 3/4/2021 | Approved | DAVID HEINE |
| Footing/Foundation/Slab | 3/4/2021 | Approved | DAVID HEINE |
| Piling/Pier/Caisson | 3/4/2021 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 3/22/2021 | Partial Approval | JUAN VALENZUELA |
| Green Building Rough | 3/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 4/22/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 4/22/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/6/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 5/6/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/20/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 5/20/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 5/20/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Interior/Exterior Lathing | 5/20/2021 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 5/20/2021 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 5/28/2021 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 5/28/2021 | Approved | BRENDAN LOONEY |
| Green Building Rough | 5/28/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 5/28/2021 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 6/8/2021 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/8/2021 | Approved | AMY COLIN |
| Shower Pan | 6/8/2021 | Approved | AMY COLIN |
| Final | 7/14/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 7/14/2021 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 7/14/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 7/14/2021 | Corrections Issued | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 8/9/2021 | SGSOV Not Ready | BRENDAN LOONEY |
| Final | 8/16/2021 | OK to Issue CofO | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 8/16/2021 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 8/16/2021 | Approved | BRENDAN LOONEY |