5517 N ALLOTT AVE 91401

Certificate Information: 5517 N ALLOTT AVE 91401

Application / Permit
20014-20000-03803
Plan Check / Job No.
B20VN11551
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 50'-3.75" x 52'-0" IRREGULAR SHAPED ADDITION AT FIRST FLOOR AND 43'-3.75" x 42'-5" IRREGULAR SHAPED ADDITION AT SECOND FLOOR. MAITAIN 14'-3" LIENEAR FOOT OF WALL. MAJOR REMODEL TO (E)SINGLE FAMILY DWELLING " NFPA 13-D FIRE SPRINKLERS THRU-OUT".
Permit Issued
Issued on 3/1/2021
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 SARKIS HARABEDIAN
Corrections Issued 9/19/2020 SARKIS HARABEDIAN
Quality Review Completed 9/22/2020 STEVEN KIM
Applicant returned to address corrections 2/4/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 2/16/2021 SARKIS HARABEDIAN
Plan Check Approved 2/26/2021 SARKIS HARABEDIAN
Issued 3/1/2021 APPLICANT
Building Plans Picked Up 12/22/2021 APPLICANT
CofO in Progress 8/26/2022 ROBERT GOLD
Permit Finaled 8/27/2022 DEROLD HAUFF
CofO Issued 8/27/2022 DEROLD HAUFF
Permit Finaled 8/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Permit Cleared 11/24/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 12/2/2020 MATTHEW CRAIG
Trees in Parkway Cleared 12/22/2020 JOHN KIM
Low Impact Development Cleared 1/12/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/25/2021 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/10/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 6/10/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/18/2021 Approved KIM BEAUCHAMP
Underground Mechanical 6/18/2021 Approved KIM BEAUCHAMP
Deputy Reinf. Concrete 6/23/2021 Conditional Approval MICHAEL TEMPLE
Excavation/Setback/Form/Re-Bar 6/30/2021 Approved ARTHUR SARGSYAN
Special/Order Compliance 7/1/2021 Corrections Issued MICHAEL TEMPLE
Deputy Steel/Welding 7/12/2021 Conditional Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2021 Partial Approval CHARLES POWELL
Wood Frame 8/4/2021 Not Ready for Inspection CHARLES POWELL
Deputy Steel/Welding 8/18/2021 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 10/6/2021 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 10/6/2021 Not Ready for Inspection RICHARD DOCKUS
Green Building Rough 10/6/2021 Approved RICHARD DOCKUS
HVAC-Rough 10/6/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 10/6/2021 Approved RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 10/6/2021 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 10/13/2021 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 11/10/2021 Not Ready for Inspection RICHARD DOCKUS
Pre-Inspection 12/3/2021 Corrections Issued MICHAEL TEMPLE
BUILDING-Rough-Frame 12/27/2021 Approved RICHARD DOCKUS
Shower Pan 12/30/2021 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 1/3/2022 Approved MARK JOHNSON
Shower Pan 1/3/2022 Approved MARK JOHNSON
Insulation 1/7/2022 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 1/7/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 1/21/2022 Approved RYAN SALAZAR
Gas Test 3/8/2022 Not Ready for Inspection RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 3/8/2022 SGSOV Not Ready RICHARD DOCKUS
Service/Power Release 3/8/2022 Not Ready for Inspection RICHARD DOCKUS
Gas Test 3/16/2022 Approved ALAN MORELOS
Green Building Final 7/22/2022 Approved RICHARD DOCKUS
HVAC-Final 7/22/2022 Corrections Issued RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 7/22/2022 Approved RICHARD DOCKUS
Final 8/1/2022 Not Ready for Inspection RICHARD DOCKUS
Final 8/22/2022 Corrections Issued RICHARD DOCKUS
HVAC-Final 8/22/2022 Not Ready for Inspection RICHARD DOCKUS
Final 8/25/2022 OK to Issue CofO ROBERT GOLD
Service/Power Release 8/25/2022 Approved ROBERT GOLD