7319 N FORBES AVE 91406

Certificate Information: 7319 N FORBES AVE 91406

Application / Permit
20014-20000-03799
Plan Check / Job No.
B20VN11544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (N) PATIO W/ DECK ABOVE (22' X 25'-6"), DEMO & ADD (N) PATIO AT FRONT (71' X 10') AND ADD CLOSET & BATHROOM (5' X 22') WITHIN (E) SFD ADJACENT TO (E) GARAGE (ALL WORK PER ENG'R)
Permit Issued
Issued on 1/3/2023
Issuing Office
Valley
Current Status
CofO in Progress on 3/12/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 NILOOFAR MEHRAIN
Corrections Issued 9/22/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/23/2020 APPLICANT
Plan Check Approved 12/8/2020 NILOOFAR MEHRAIN
Issued 1/3/2023 APPLICANT
CofO in Progress 3/11/2026 VINCENT HANLEY
No Progress 3/12/2026 VINCENT HANLEY
CofO in Progress 3/12/2026 VINCENT HANLEY
CofO in Progress 3/12/2026 VINCENT HANLEY

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/30/2020 ADRIAN CASTRO
Low Impact Development Cleared 3/31/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 11/17/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2023 Conditional Approval ROBERT GOLD
Underground Mechanical 3/23/2023 Corrections Issued RAUL OLAGI
Underground Mechanical 6/7/2023 Corrections Issued RAUL OLAGI
Footing/Foundation/Slab 9/29/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 8/15/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 8/15/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Rough 8/15/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/15/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 8/21/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 8/21/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 9/9/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 9/9/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 11/19/2024 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 11/19/2024 Partial Approval SALVADOR MARTINEZ
Green Building Rough 11/19/2024 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 12/6/2024 Corrections Issued SALVADOR MARTINEZ
Insulation 12/6/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 2/4/2025 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 2/4/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 2/4/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/30/2025 Partial Approval GAREN HAYRAPETYAN
Shower Pan 4/30/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 8/11/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/10/2026 Approved VINCENT HANLEY
ELECTRICAL-Final 3/10/2026 Approved VINCENT HANLEY
Final 3/10/2026 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 3/10/2026 Approved VINCENT HANLEY
Green Building Final 3/10/2026 Approved VINCENT HANLEY
Green Building Rough 3/10/2026 Approved VINCENT HANLEY
HVAC-Final 3/10/2026 Approved VINCENT HANLEY
PLUMBING-Final 3/10/2026 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 3/10/2026 SGSOV Approved VINCENT HANLEY
Smoke Detectors 3/10/2026 Approved VINCENT HANLEY
Special/Order Compliance 3/12/2026 Corrections Issued VINCENT HANLEY