11676 W COLLINS ST 91601
Certificate Information: 11676 W COLLINS ST 91601
- Application / Permit
- 20014-20000-03772
- Plan Check / Job No.
- B20VN11479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR ADDITIONAL TO ADD BASEMENT AND 2ND FLOOR TO (E) 1 STORY BUILDING ( FIRE SPRINKLES NFPA-13D )
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 9/26/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/15/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/20/2020 | APPLICANT |
| Applicant returned to address corrections | 11/16/2021 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/31/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/15/2022 | MOHAMMAD ESMAILI |
| Issued | 3/15/2022 | APPLICANT |
| CofO in Progress | 8/9/2024 | CHRISTOPHER ROJAS |
| CofO in Progress | 10/2/2024 | JUAN VALENZUELA |
| CofO in Progress | 10/2/2024 | JUAN VALENZUELA |
| CofO in Progress | 10/2/2024 | JUAN VALENZUELA |
| Permit Finaled | 10/30/2024 | DANIEL ORRANTE |
| CofO Issued | 10/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/13/2021 | GABRIEL ROBLES |
| Low Impact Development | Cleared | 9/7/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 9/16/2021 | GABRIEL ROBLES |
| Excavation more than 5-ft deep | Cleared | 3/15/2022 | CALOSHA APPROVED |
| Miscellaneous | Cleared | 3/15/2022 | MOHAMMAD ESMAILI |
Contact Information
| Architect | , ; Lic. No.: C0 | , |
| Architect | Humphries,, Douglas S; Lic. No.: C25559 | 12122 HARTSOOK STREET VALLEY VILLAGE, CA 91607 |
| Contractor | Mike'S Building Corp; Lic. No.: 803105-B | 16046 BLYTHE STREET VAN NUYS, CA 91406 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 5/26/2022 | Not Ready for Inspection | KIRK LINKLATER |
| Deputy Other (see comments) | 12/20/2022 | Conditional Approval | MICHAEL SMITH |
| Excavation/Setback/Form/Re-Bar | 3/9/2023 | Approved | JACK KARGODORIAN |
| Wood Frame | 4/19/2023 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 5/30/2023 | Partial Approval | JACK KARGODORIAN |
| MERV13>=Rough | 6/30/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Wood Frame | 7/17/2023 | Partial Approval | JACK KARGODORIAN |
| Pre-Inspection | 7/20/2023 | Partial Approval | JACK KARGODORIAN |
| Gas Test | 8/2/2023 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 8/2/2023 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 10/12/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 10/12/2023 | Approved | RYAN SALAZAR |
| Insulation | 11/1/2023 | Corrections Issued | JOHN COLEMAN |
| Interior/Exterior Lathing | 11/1/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 11/1/2023 | Approved | JOHN COLEMAN |
| Insulation | 11/4/2023 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/21/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 11/21/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 11/21/2023 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/21/2023 | Approved | JUAN VALENZUELA |
| MERV13>=Rough | 11/21/2023 | Approved | JUAN VALENZUELA |
| Gas Test | 1/19/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 3/13/2024 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 3/13/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 3/13/2024 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 3/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 3/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/29/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 5/14/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 5/14/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 5/14/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 5/14/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 5/28/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 5/28/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 5/28/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Final | 5/28/2024 | Approved | CHRISTOPHER ROJAS |
| Reinforced Concrete Frame | 5/28/2024 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 5/28/2024 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 5/28/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 8/7/2024 | OK to Issue CofO | CHRISTOPHER ROJAS |