1916 1/2 W 77TH ST 90047
Certificate Information: 1916 1/2 W 77TH ST 90047
- Application / Permit
- 20014-20000-03766
- Plan Check / Job No.
- B20VN11464
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU PER LAMC 12.2233(c) & (d) WITH AN ADDITION AT REAR OF THE LOT.
- Permit Issued
- Issued on 5/3/2021
- Issuing Office
- Current Status
- Issued on 5/3/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2020 | JAHANSHAH POURHASSAN |
| Corrections Issued | 9/19/2020 | JAHANSHAH POURHASSAN |
| Plan Check Approved | 2/2/2021 | ALFREDO JARA |
| Building Plans Picked Up | 2/5/2021 | APPLICANT |
| Issued | 5/3/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 9/30/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2020 | CELINA MORENO |
| Sewer availability | Cleared | 10/1/2020 | CELINA MORENO |
| Construction near power lines | Cleared | 12/15/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/7/2021 | MATTHEW CRAIG |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Concept Renovations Inc; Lic. No.: 1016942-B | 15928 VENTURA BLVD 225 ENCINO, CA 91436 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/7/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/7/2021 | Partial Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/14/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/14/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 6/14/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 6/21/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 6/21/2021 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 6/21/2021 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 7/15/2021 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/15/2021 | Partial Approval | JESUS RODRIGUEZ |
| HVAC-Rough | 8/3/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 8/3/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/6/2021 | No Access for Inspection | FREDDIE RIVERA |
| Green Building Rough | 8/6/2021 | No Access for Inspection | FREDDIE RIVERA |
| Wood Frame | 8/6/2021 | No Access for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 8/10/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 8/10/2021 | Approved | FREDDIE RIVERA |
| Wood Frame | 8/10/2021 | Approved | FREDDIE RIVERA |
| Insulation | 8/24/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 8/30/2021 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 9/23/2021 | Approved | FREDDIE RIVERA |
| Shower Pan | 9/23/2021 | Approved | FREDDIE RIVERA |
| Final | 1/13/2022 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 1/13/2022 | Approved | FREDDIE RIVERA |
| Green Building Final | 1/13/2022 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 1/13/2022 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 1/13/2022 | Approved | FREDDIE RIVERA |
| Sewer | 2/4/2022 | Approved | FREDDIE RIVERA |
| Final | 2/28/2022 | Conditional Approval | FREDDIE RIVERA |