911 S NORTON AVE 90019
Certificate Information: 911 S NORTON AVE 90019
- Application / Permit
- 20014-20000-03756
- Plan Check / Job No.
- B20VN11427
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (18) School Building
- Work Description
- NEW 24'11' X 16'5" ADDITION OF A NEW ELEVATOR , MECHANICAL ROOM , PATIO COVER WITH DECK ABOVE , INTERIOR REMODEL AT 1ST FLOOR FOR CLASROOMS , BATHROOMS , AUDITORIUM , KITCHEN AND OFFICE , INTERIOR REMODEL AT 2ND FLOOR FOR OFFICES , BATHROOMS , BREAKROOM , EXTERIOR REPAIR TO DECKS AND GUARDRAIL, NEW HVAC ROOFTOP UNITS (6) UNITS (850 LBS EACH ) AND (6) PUMPS (295 LBS ) , (1) FAN (151 LBS) , DOORS AND WINDOWS CHANGEOUT, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 4/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/29/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2020 | APPLICANT |
| Application Withdrawn | 9/15/2020 | APPLICANT |
| Re-Activate Applicaton | 9/15/2020 | APPLICANT |
| Disabled Access Plans Picked Up | 10/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | RARES BODEA |
| Corrections Issued | 10/10/2020 | RARES BODEA |
| Quality Review Completed | 10/16/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/20/2020 | APPLICANT |
| Green Plans Picked Up | 10/20/2020 | APPLICANT |
| Applicant returned to address corrections | 1/24/2022 | RARES BODEA |
| Plan Check Approved | 2/18/2022 | RARES BODEA |
| Issued | 4/28/2022 | APPLICANT |
| CofO Issued | 4/29/2025 | ERNESTO CORRAL |
| Permit Finaled | 4/29/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| CPC | Cleared | 12/3/2020 | KENTON TRINH |
| ZA Case | Cleared | 12/3/2020 | KENTON TRINH |
| ZA Case | Cleared | 12/3/2020 | KENTON TRINH |
| ZA Case | Cleared | 12/3/2020 | KENTON TRINH |
| ZA Case | Cleared | 12/3/2020 | KENTON TRINH |
| Hydrant and Access approval | Cleared | 12/22/2020 | MATTHEW CRAIG |
| HPOZ | Cleared | 12/31/2020 | AMANDA KAINER |
| ZI | Cleared | 12/31/2020 | AMANDA KAINER |
| Certificate of Compliance | Cleared | 3/10/2021 | MARC WOERSCHING |
| Low Impact Development | Cleared | 7/1/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/8/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | WALLIE JONG |
| Food Service Establishment | Cleared | 7/22/2021 | PAWAN VERMA |
| Fire Marshal Fire Life Safety | Cleared | 11/3/2021 | ANDREW KO |
| Green Code | Cleared | 12/9/2021 | RICHARD GARCIA |
| DAS Clearance | Cleared | 12/16/2021 | RARES BODEA |
| Food establishment approval | Cleared | 1/24/2022 | LACDHS APPROVED |
Contact Information
| Architect | Kerr,, Robert E; Lic. No.: C28038 | 2551 S BUNDY DRIVE LOS ANGELES, CA 90064 |
| Contractor | Vancrest Construction Corp; Lic. No.: 393800-B | 7171 NORTH FIGUEROA STREET LOS ANGELES, CA 90042 |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 1423 S BEVERLY GLEN BLVD APT B LOS ANGELES, CA 90024 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/25/2022 | Corrections Issued | MARK FERRARI |
| Light Gage Steel Frame | 6/1/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 6/6/2022 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Partial Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 6/6/2022 | Partial Inspection | KATY RAMIREZ |
| Green Building Rough | 6/6/2022 | Approved | KATY RAMIREZ |
| Light Gage Steel Frame | 6/6/2022 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 6/14/2022 | Partial Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | No Access for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 6/17/2022 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 6/28/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 8/2/2022 | Conditional Approval | WINSTON DUNNING |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Partial Inspection | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 8/11/2022 | Partial Approval | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 8/25/2022 | Conditional Approval | WINSTON DUNNING |
| Drywall Nailing | 8/26/2022 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 8/26/2022 | Partial Approval | KATY RAMIREZ |
| Deputy Drilled-In Anchors | 9/1/2022 | Conditional Approval | KATY RAMIREZ |
| Deputy Wood Construction | 9/1/2022 | Conditional Approval | WINSTON DUNNING |
| Drywall Nailing | 9/2/2022 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 9/2/2022 | Partial Approval | KATY RAMIREZ |
| Wood Frame | 9/13/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 9/14/2022 | Partial Approval | KATY RAMIREZ |
| Insulation | 9/27/2022 | Partial Approval | KATY RAMIREZ |
| Interior/Exterior Lathing | 10/7/2022 | Partial Approval | RAFAEL ESPINOZA |
| Light Gage Steel Frame | 10/31/2022 | Corrections Issued | KATY RAMIREZ |
| Light Gage Steel Frame | 11/4/2022 | Partial Approval | KATY RAMIREZ |
| Insulation | 11/8/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 11/10/2022 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 12/2/2022 | Partial Approval | RAFAEL ESPINOZA |
| Drywall Nailing | 12/7/2022 | Approved | RAFAEL CORTES |
| T-Bar Ceiling | 1/27/2023 | Partial Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 2/13/2023 | Partial Approval | ALFREDO LOPEZ |
| Final | 7/12/2024 | Partial Inspection | JACOB MYERS |
| Green Building Final | 7/12/2024 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 7/12/2024 | SGSOV Not Ready | JACOB MYERS |
| Smoke Detectors | 7/12/2024 | Partial Inspection | JACOB MYERS |
| Wood Frame | 7/12/2024 | Partial Inspection | JACOB MYERS |
| Final | 4/7/2025 | Conditional Approval | MARTIN TAVITIAN |
| Green Building Final | 4/7/2025 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 4/7/2025 | Approved | MARTIN TAVITIAN |
| Wood Frame | 4/7/2025 | Approved | MARTIN TAVITIAN |