951 N MICHELTORENA ST 90026
Certificate Information: 951 N MICHELTORENA ST 90026
- Application / Permit
- 20014-20000-03749
- Plan Check / Job No.
- B20VN11407
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & ADDITION OF 2ND STORY STAIR SHAFT TO (E) 1STORY SFD AND ROOF DECK ;FIRE SPRINKLERS NFPA 13D ,REQ'D
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/5/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/26/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 10/27/2020 | APPLICANT |
| Applicant returned to address corrections | 1/19/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 5/18/2022 | MOHAMMAD ESMAILI |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 1/8/2026 | FREDDIE RIVERA |
| CofO in Progress | 1/8/2026 | FREDDIE RIVERA |
| CofO in Progress | 1/13/2026 | FREDDIE RIVERA |
| Permit Finaled | 1/13/2026 | DEROLD HAUFF |
| CofO Issued | 1/13/2026 | DEROLD HAUFF |
| Permit Finaled | 1/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 12/31/2020 | DANG NGUYEN |
| Low Impact Development | Cleared | 10/20/2021 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2021 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 10/29/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 10/29/2021 | CHRISTOPHER ROCHA |
| GPI Written Notices | Cleared | 5/11/2022 | MOHAMMAD ESMAILI |
| Grading Pre-Inspection | Cleared | 5/11/2022 | MOHAMMAD ESMAILI |
Contact Information
| Architect | , ; Lic. No.: C33595 | , |
| Contractor | Pacific Coast Developers; Lic. No.: 888234-B | 5249 BECKFORD AVENUE TARZANA, CA 91356 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/28/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 4/25/2023 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Partial Approval | FREDDIE RIVERA |
| Deputy Reinf. Concrete | 5/15/2023 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/16/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 5/24/2023 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 6/2/2023 | Partial Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 6/9/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/19/2023 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 8/2/2023 | No Access for Inspection | FREDDIE RIVERA |
| Deputy Steel/Welding | 9/26/2023 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 10/30/2023 | Partial Approval | FREDDIE RIVERA |
| Wood Frame | 10/30/2023 | OK to Expire Permit | FREDDIE RIVERA |
| Insulation | 11/6/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2024 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2024 | Conditional Approval | FREDDIE RIVERA |
| Green Building Rough | 11/21/2024 | Partial Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 11/21/2024 | Partial Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 1/3/2025 | Corrections Issued | BRENDAN MORELLI |
| Interior/Exterior Lathing | 1/7/2025 | Partial Approval | FREDDIE RIVERA |
| HVAC-Rough | 1/10/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/15/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/15/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 1/15/2025 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 1/15/2025 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 1/15/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 1/24/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 1/29/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 1/29/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/3/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 2/3/2025 | Partial Inspection | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 3/12/2025 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/19/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/19/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/19/2025 | Partial Approval | FREDDIE RIVERA |
| Insulation | 4/16/2025 | Corrections Issued | REGINA MENDEZ |
| Drywall Nailing | 6/18/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 7/3/2025 | Approved | ALEX COLIN |
| Shower Pan | 7/3/2025 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 10/28/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 11/3/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 11/3/2025 | Approved | FREDDIE RIVERA |
| Final | 11/14/2025 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 11/14/2025 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2025 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 11/14/2025 | Approved | FREDDIE RIVERA |
| Final | 1/2/2026 | Corrections Issued | WILLIAM SIERRA |
| Final | 1/7/2026 | OK to Issue CofO | FREDDIE RIVERA |
| Service/Power Release | 1/7/2026 | Approved | FREDDIE RIVERA |
| Service/Power Release | 1/8/2026 | Corrections Issued | FREDDIE RIVERA |