951 N MICHELTORENA ST 90026

Certificate Information: 951 N MICHELTORENA ST 90026

Application / Permit
20014-20000-03749
Plan Check / Job No.
B20VN11407
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION OF 2ND STORY STAIR SHAFT TO (E) 1STORY SFD AND ROOF DECK ;FIRE SPRINKLERS NFPA 13D ,REQ'D
Permit Issued
Issued on 10/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 MOHAMMAD ESMAILI
Corrections Issued 10/5/2020 MOHAMMAD ESMAILI
Quality Review Completed 10/26/2020 OMID HEDAYAT
Building Plans Picked Up 10/27/2020 APPLICANT
Applicant returned to address corrections 1/19/2022 MOHAMMAD ESMAILI
Plan Check Approved 5/18/2022 MOHAMMAD ESMAILI
Issued 10/27/2022 APPLICANT
CofO in Progress 1/8/2026 FREDDIE RIVERA
CofO in Progress 1/8/2026 FREDDIE RIVERA
CofO in Progress 1/13/2026 FREDDIE RIVERA
Permit Finaled 1/13/2026 DEROLD HAUFF
CofO Issued 1/13/2026 DEROLD HAUFF
Permit Finaled 1/13/2026 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 12/31/2020 DANG NGUYEN
Low Impact Development Cleared 10/20/2021 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 10/29/2021 CHRISTOPHER ROCHA
Roof/Waste drainage to street Cleared 10/29/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 10/29/2021 CHRISTOPHER ROCHA
GPI Written Notices Cleared 5/11/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 5/11/2022 MOHAMMAD ESMAILI

Contact Information

Architect , ; Lic. No.: C33595       ,
Contractor Pacific Coast Developers; Lic. No.: 888234-B 5249 BECKFORD AVENUE      TARZANA, CA 91356

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 4/25/2023 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 5/3/2023 Partial Approval FREDDIE RIVERA
Deputy Reinf. Concrete 5/15/2023 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 5/16/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/24/2023 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 6/2/2023 Partial Inspection FREDDIE RIVERA
Special/Order Compliance 6/9/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 7/19/2023 Approved FREDDIE RIVERA
Interior/Exterior Lathing 8/2/2023 No Access for Inspection FREDDIE RIVERA
Deputy Steel/Welding 9/26/2023 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 10/30/2023 Partial Approval FREDDIE RIVERA
Wood Frame 10/30/2023 OK to Expire Permit FREDDIE RIVERA
Insulation 11/6/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/16/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/21/2024 Conditional Approval FREDDIE RIVERA
Green Building Rough 11/21/2024 Partial Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 11/21/2024 Partial Inspection FREDDIE RIVERA
Interior/Exterior Lathing 1/3/2025 Corrections Issued BRENDAN MORELLI
Interior/Exterior Lathing 1/7/2025 Partial Approval FREDDIE RIVERA
HVAC-Rough 1/10/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 1/15/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 1/15/2025 Approved FREDDIE RIVERA
Green Building Rough 1/15/2025 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 1/15/2025 Corrections Issued FREDDIE RIVERA
Verify Sprinkler Sign Off 1/15/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 1/24/2025 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 1/29/2025 Partial Inspection FREDDIE RIVERA
Green Building Rough 1/29/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 2/3/2025 Corrections Issued FREDDIE RIVERA
Green Building Rough 2/3/2025 Partial Inspection FREDDIE RIVERA
Deputy Drilled-In Anchors 3/12/2025 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/19/2025 Approved FREDDIE RIVERA
Green Building Rough 3/19/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/19/2025 Partial Approval FREDDIE RIVERA
Insulation 4/16/2025 Corrections Issued REGINA MENDEZ
Drywall Nailing 6/18/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 7/3/2025 Approved ALEX COLIN
Shower Pan 7/3/2025 Approved ALEX COLIN
ELECTRICAL-Final 10/28/2025 Approved FREDDIE RIVERA
HVAC-Final 11/3/2025 Approved FREDDIE RIVERA
PLUMBING-Final 11/3/2025 Approved FREDDIE RIVERA
Final 11/14/2025 Corrections Issued FREDDIE RIVERA
Green Building Final 11/14/2025 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/14/2025 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 11/14/2025 Approved FREDDIE RIVERA
Final 1/2/2026 Corrections Issued WILLIAM SIERRA
Final 1/7/2026 OK to Issue CofO FREDDIE RIVERA
Service/Power Release 1/7/2026 Approved FREDDIE RIVERA
Service/Power Release 1/8/2026 Corrections Issued FREDDIE RIVERA