123 S KILKEA DR 90048

Certificate Information: 123 S KILKEA DR 90048

Application / Permit
20014-20000-03734
Plan Check / Job No.
B20VN11350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel throughout (removing and replacing most of the (E) SFD) with addition to rear of SFD. addition 365sqft
Permit Issued
Issued on 4/8/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Assigned to Plan Check Engineer 9/16/2020 JAHANSHAH POURHASSAN
Corrections Issued 9/19/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 11/13/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 12/23/2020 MANUEL GARCIA
Applicant returned to address corrections 1/25/2021 JASON JANGADA
Applicant returned to address corrections 2/4/2021 MANUEL GARCIA
Building Plans Picked Up 2/5/2021 APPLICANT
Plan Check Approved 2/22/2021 KHUONG TRUONG
Issued 4/8/2021 APPLICANT
CofO in Progress 10/4/2022 EVAN COOPER
CofO in Progress 10/11/2022 EVAN COOPER
Permit Finaled 10/19/2022 DANIEL ORRANTE
CofO Issued 10/19/2022 DANIEL ORRANTE
Permit Finaled 10/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/8/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 1/5/2021 CELINA MORENO
Sewer availability Cleared 1/5/2021 CELINA MORENO
Hold Cleared 3/22/2021 JASON SHEETS

Contact Information

Contractor Dosh Construction Inc; Lic. No.: 1064567-B 14721 OXNARD ST      VAN NUYS, CA 91411
Engineer Mroczka,, Peter J; Lic. No.: C42648 9301 DARBY AVE APT 1      NORTHRIDGE, CA 91325

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/13/2021 Partial Approval EVAN COOPER
METHANE-Barrier 4/13/2021 Approved EVAN COOPER
METHANE-Subgrade 4/13/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 5/3/2021 Partial Approval EVAN COOPER
Green Building Rough 5/3/2021 Not Ready for Inspection EVAN COOPER
METHANE-Rough 5/3/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/4/2021 Partial Approval EVAN COOPER
HVAC-Rough 8/9/2021 Corrections Issued EVAN COOPER
ELECTRICAL-Rough 8/10/2021 Approved EVAN COOPER
PLUMBING-Rough 8/19/2021 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 8/23/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 8/25/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 8/25/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 8/27/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 9/2/2021 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Partial Approval EVAN COOPER
Green Building Rough 9/2/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 12/14/2021 Corrections Issued EVAN COOPER
Green Building Rough 12/14/2021 Not Ready for Inspection EVAN COOPER
Interior/Exterior Lathing 12/16/2021 Partial Approval EVAN COOPER
Green Building Rough 12/22/2021 Approved EVAN COOPER
HVAC-Rough 12/22/2021 Approved EVAN COOPER
Insulation 12/22/2021 Approved EVAN COOPER
Shower Pan 12/22/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 12/22/2021 Approved EVAN COOPER
Drywall Nailing 12/28/2021 Not Ready for Inspection EVAN COOPER
Green Building Rough 12/28/2021 Approved EVAN COOPER
Drywall Nailing 12/29/2021 Approved EVAN COOPER
Interior/Exterior Lathing 1/4/2022 Approved EVAN COOPER
Sewer 5/19/2022 Corrections Issued EVAN COOPER
PLUMBING-Rough 6/23/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 8/11/2022 Approved EVAN COOPER
Final 8/11/2022 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 8/11/2022 Approved EVAN COOPER
Green Building Final 8/11/2022 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Not Ready EVAN COOPER
Smoke Detectors 8/11/2022 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Final 9/21/2022 Corrections Issued EVAN COOPER
Final 9/21/2022 Corrections Issued EVAN COOPER
Green Building Final 9/21/2022 Corrections Issued EVAN COOPER
PLUMBING-Final 9/21/2022 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/21/2022 SGSOV Approved EVAN COOPER
Service/Power Release 9/21/2022 Approved EVAN COOPER
Smoke Detectors 9/21/2022 Approved EVAN COOPER
ELECTRICAL-Final 10/4/2022 Approved EVAN COOPER
Final 10/4/2022 OK to Issue CofO EVAN COOPER
Green Building Final 10/4/2022 Approved EVAN COOPER
HVAC-Final 10/4/2022 Approved EVAN COOPER
PLUMBING-Final 10/4/2022 Approved EVAN COOPER
Final 10/11/2022 OK to Issue CofO EVAN COOPER
Pre-Inspection 10/11/2022 Approved EVAN COOPER
Underground Mechanical 10/11/2022 Approved EVAN COOPER
Wood Frame 10/11/2022 Approved EVAN COOPER