7025 N SYLVIA AVE 91335

Certificate Information: 7025 N SYLVIA AVE 91335

Application / Permit
20014-20000-03731
Plan Check / Job No.
B20VN11366
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL (1) BATHROOM, CONVERT LAUNDRY TO BATHROOM, CONVERT BEDROOM TO FAMILY ROOM/LAUNDRY AND 17' 4" X 14' 11" MASTER BEDROOMCLOSET ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 10/9/2020
Issuing Office
Current Status
CofO Issued on 5/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 GURUNATH NESARAJAH
Corrections Issued 9/6/2020 GURUNATH NESARAJAH
Plan Check Approved 10/9/2020 GURUNATH NESARAJAH
Issued 10/9/2020 APPLICANT
CofO in Progress 4/22/2022 VINCENT HANLEY
CofO Issued 5/14/2022 MICHAEL SMITH
Permit Finaled 5/14/2022 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 9/11/2020 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 9/24/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 9/24/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/6/2020 Approved VINCENT HANLEY
PLUMBING-Rough 11/6/2020 Partial Approval VINCENT HANLEY
Sewer 11/6/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/18/2020 Partial Approval VINCENT HANLEY
Green Building Rough 11/18/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 11/18/2020 Partial Approval VINCENT HANLEY
Insulation 11/20/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/24/2020 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/2/2020 Approved VINCENT HANLEY
Wood Frame 12/2/2020 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 1/7/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 1/7/2021 Approved VINCENT HANLEY
Green Building Rough 1/7/2021 Approved VINCENT HANLEY
HVAC-Rough 1/7/2021 Approved VINCENT HANLEY
PLUMBING-Rough 1/7/2021 Approved VINCENT HANLEY
Insulation 1/11/2021 Approved VINCENT HANLEY
Drywall Nailing 1/15/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/15/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 12/14/2021 Approved VINCENT HANLEY
Final 12/14/2021 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 12/14/2021 Approved VINCENT HANLEY
Green Building Final 12/14/2021 Approved VINCENT HANLEY
HVAC-Final 12/14/2021 Approved VINCENT HANLEY
PLUMBING-Final 12/14/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/14/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 12/14/2021 Approved VINCENT HANLEY