7025 N SYLVIA AVE 91335
Certificate Information: 7025 N SYLVIA AVE 91335
- Application / Permit
- 20014-20000-03731
- Plan Check / Job No.
- B20VN11366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (1) BATHROOM, CONVERT LAUNDRY TO BATHROOM, CONVERT BEDROOM TO FAMILY ROOM/LAUNDRY AND 17' 4" X 14' 11" MASTER BEDROOMCLOSET ADDITION TO REAR OF (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 9/6/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/9/2020 | GURUNATH NESARAJAH |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 4/22/2022 | VINCENT HANLEY |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| ZI | Cleared | 9/11/2020 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 9/24/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/6/2020 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 11/6/2020 | Partial Approval | VINCENT HANLEY |
| Sewer | 11/6/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 11/18/2020 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 11/18/2020 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 11/18/2020 | Partial Approval | VINCENT HANLEY |
| Insulation | 11/20/2020 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2020 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2020 | Approved | VINCENT HANLEY |
| Wood Frame | 12/2/2020 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 1/7/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/7/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/7/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 1/7/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 1/7/2021 | Approved | VINCENT HANLEY |
| Insulation | 1/11/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 1/15/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 1/15/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 12/14/2021 | Approved | VINCENT HANLEY |
| Final | 12/14/2021 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 12/14/2021 | Approved | VINCENT HANLEY |
| Green Building Final | 12/14/2021 | Approved | VINCENT HANLEY |
| HVAC-Final | 12/14/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 12/14/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/14/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 12/14/2021 | Approved | VINCENT HANLEY |