15330 W COBALT ST 91342

Certificate Information: 15330 W COBALT ST 91342

Application / Permit
20014-20000-03726
Plan Check / Job No.
B20VN11355
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL KITCHEN, RELOCATE LAUNDRY AND 2' 8" X 10' ADDITION TO (E) SFD. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 10/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 GURUNATH NESARAJAH
Corrections Issued 9/7/2020 GURUNATH NESARAJAH
Plan Check Approved 9/30/2020 GURUNATH NESARAJAH
Issued 10/19/2020 APPLICANT
CofO in Progress 11/2/2021 JENNIFER RABUCHIN
Permit Finaled 8/31/2022 DANIEL ORRANTE
CofO Issued 8/31/2022 DANIEL ORRANTE
Permit Finaled 8/31/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/14/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 9/14/2020 GABRIEL ROBLES

Contact Information

Contractor R R R Construction Inc; Lic. No.: 730949-B 34501 RD 204      WOODLAKE, CA 93286

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/18/2021 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 5/18/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 6/23/2021 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 6/23/2021 Not Ready for Inspection MISAEL ESPARZA
Insulation 6/23/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 6/23/2021 Corrections Issued MISAEL ESPARZA
Pre-Inspection 6/23/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 6/28/2021 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 6/28/2021 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 6/28/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 6/28/2021 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 6/30/2021 Approved DANIEL ORRANTE
PLUMBING-Rough 6/30/2021 Approved DANIEL ORRANTE
Drywall Nailing 7/7/2021 Conditional Approval DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 7/7/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 7/21/2021 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 9/22/2021 Not Ready for Inspection JOHN HAYES
Final 9/22/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 9/22/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 9/22/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 9/22/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 10/29/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 10/29/2021 Approved JENNIFER RABUCHIN
Final 10/29/2021 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 10/29/2021 Approved JENNIFER RABUCHIN
Green Building Rough 10/29/2021 Approved JENNIFER RABUCHIN
HVAC-Final 10/29/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 10/29/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 10/29/2021 Approved JENNIFER RABUCHIN