4934 N BELLAIRE AVE 91607

Certificate Information: 4934 N BELLAIRE AVE 91607

Application / Permit
20014-20000-03722
Plan Check / Job No.
B20VN11340
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
432 SQ. FT. ADDITION AND REMODEL TO (E) SFD TO ENLARGE THE (E) MASTER BEDROOM AND DINING ROOM.
Permit Issued
Issued on 5/3/2021
Issuing Office
Current Status
CofO Issued on 10/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 ALFREDO JARA
Corrections Issued 9/14/2020 ALFREDO JARA
Applicant returned to address corrections 12/10/2020 MOHAMMAD ESMAILI
Building Plans Picked Up 1/6/2021 APPLICANT
Applicant returned to address corrections 3/9/2021 MARJAN SHENASI
Plan Check Approved 4/29/2021 ALFREDO JARA
Issued 5/3/2021 APPLICANT
CofO in Progress 9/10/2021 CHRISTOPHE COCHRAN
CofO in Progress 9/10/2021 CHRISTOPHE COCHRAN
Permit Finaled 10/25/2021 MICHAEL SMITH
CofO Issued 10/25/2021 MICHAEL SMITH
Permit Finaled 10/25/2021 MICHAEL SMITH

Permit Application Clearance Information

Hold Cleared 1/28/2021 JASON SHEETS
Specific Plan Cleared 2/3/2021 ERIN NASH
Low Impact Development Cleared 4/19/2021 YVAINNE GALSIM
Eng Process Fee Ord 176,300 Cleared 4/21/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 4/21/2021 ADRIAN CASTRO

Contact Information

Contractor Form Architectural; Lic. No.: 442000-B 17721 VALLEY VISTA BLVD      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/10/2021 Approved ARAM AVEDISIAN
HVAC-Rough 5/18/2021 Approved RICHARD DOCKUS
Rough-Elec/Plmb/HVAC 5/21/2021 Partial Approval RICHARD DOCKUS
Drywall Nailing 5/24/2021 Partial Approval RICHARD DOCKUS
Green Building Rough 5/24/2021 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 6/16/2021 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 6/16/2021 Partial Approval ARTHUR SARGSYAN
Insulation 6/16/2021 Partial Approval ARTHUR SARGSYAN
Interior/Exterior Lathing 6/16/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 6/23/2021 Approved RICHARD DOCKUS
Green Building Rough 6/23/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/23/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 8/24/2021 SGSOV Not Ready CHRISTOPHE COCHRAN
Final 8/26/2021 Corrections Issued CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 9/2/2021 Approved CHRISTOPHE COCHRAN
Final 9/2/2021 OK to Issue CofO CHRISTOPHE COCHRAN
Footing/Foundation/Slab 9/2/2021 Approved CHRISTOPHE COCHRAN
Green Building Final 9/2/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 9/2/2021 Approved CHRISTOPHE COCHRAN