24633 W EILAT ST 91367
Certificate Information: 24633 W EILAT ST 91367
- Application / Permit
- 20014-20000-03713
- Plan Check / Job No.
- B20VN11320
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 38'6"X58'0" 2ND STORY ADDITION & REMODEL TO (E) SFD. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT
- Permit Issued
- Issued on 12/23/2021
- Issuing Office
- Valley
- Current Status
- Issued on 12/23/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | MARVEL DELACRUZ |
| Corrections Issued | 9/29/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 10/6/2020 | STEVEN KIM |
| Building Plans Picked Up | 10/7/2020 | APPLICANT |
| Applicant returned to address corrections | 9/3/2021 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 10/22/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 12/16/2021 | MARVEL DELACRUZ |
| Issued | 12/23/2021 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 4/6/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 4/7/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 5/5/2021 | MARTIN FRAGOSO |
| Trees in Parkway | Cleared | 7/8/2021 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 7/23/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | DAGOVERTO GUERRERO |
| Green Code | Cleared | 9/3/2021 | MARVEL DELACRUZ |
| GPI Written Notices | Cleared | 10/6/2021 | MANUEL TEJADA |
| Miscellaneous | Cleared | 10/12/2021 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/12/2021 | STEVEN WECHSLER |
| Grading Pre-Inspection | Cleared | 12/6/2021 | ALEXANDER HELFER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Donlong Peter; Lic. No.: S3948 | 8748 E VALLEY BLVD L ROSEMEAD, CA 91770 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/4/2022 | Partial Approval | TROY SANDERS |
| Sewer | 5/4/2022 | Approved | TROY SANDERS |
| Excavation/Setback/Form/Re-Bar | 5/9/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 6/9/2022 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Partial Approval | TROY SANDERS |
| Green Building Rough | 6/28/2022 | Not Ready for Inspection | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/18/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 10/24/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 11/7/2022 | No Access for Inspection | TROY SANDERS |
| HVAC-Rough | 11/7/2022 | No Access for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 11/10/2022 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 11/10/2022 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Rough | 11/30/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 11/30/2022 | Approved | TROY SANDERS |
| Shower Pan | 12/22/2022 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 12/28/2022 | Conditional Approval | TROY SANDERS |
| Green Building Rough | 12/28/2022 | Approved | TROY SANDERS |
| Special/Order Compliance | 12/28/2022 | Corrections Issued | TROY SANDERS |
| Verify Sprinkler Sign Off | 12/28/2022 | Approved | TROY SANDERS |
| Deputy Wood Construction | 1/20/2023 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/27/2023 | Conditional Approval | TROY SANDERS |
| Green Building Rough | 2/21/2023 | Approved | TROY SANDERS |
| Insulation | 2/21/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/21/2023 | Partial Approval | TROY SANDERS |
| Insulation | 2/23/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/23/2023 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 3/7/2023 | Approved | TROY SANDERS |
| Special/Order Compliance | 3/7/2023 | Partial Inspection | MORRIS JACKSON |
| Shower Pan | 5/26/2023 | No Access for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 5/31/2023 | Partial Approval | TROY SANDERS |
| Shower Pan | 5/31/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 12/20/2024 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 12/20/2024 | Approved | TROY SANDERS |
| Final | 12/20/2024 | Corrections Issued | TROY SANDERS |
| Footing/Foundation/Slab | 12/20/2024 | Approved | TROY SANDERS |
| Green Building Final | 12/20/2024 | Not Ready for Inspection | TROY SANDERS |
| HVAC-Final | 12/20/2024 | Approved | TROY SANDERS |
| PLUMBING-Final | 12/20/2024 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/20/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 12/20/2024 | Approved | TROY SANDERS |