22650-22652 W SHERMAN WAY 91307

Certificate Information: 22650-22652 W SHERMAN WAY 91307

Application / Permit
20014-20000-03711
Plan Check / Job No.
B20VN11314
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) GUEST HOUSE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (e) AND ATTACH TO (E) SFD WITH (N) BEDROOM
Permit Issued
Issued on 1/20/2022
Issuing Office
Current Status
Issued on 1/20/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/11/2020 NILOOFAR MEHRAIN
Corrections Issued 9/15/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 9/18/2020 APPLICANT
Applicant returned to address corrections 12/8/2020 NILOOFAR MEHRAIN
Applicant returned to address corrections 1/26/2021 NILOOFAR MEHRAIN
Plan Check Approved 8/16/2021 NILOOFAR MEHRAIN
No Progress 8/16/2021 NILOOFAR MEHRAIN
Plan Check Approved 8/16/2021 NILOOFAR MEHRAIN
Issued 1/20/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/8/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/8/2021 ADRIAN CASTRO
Sewer availability Cleared 1/8/2021 ADRIAN CASTRO
Low Impact Development Cleared 8/4/2021 ANDRES COVARRUBIAS
Miscellaneous Cleared 8/11/2021 LAUREN PADICK
Miscellaneous Cleared 8/11/2021 LAUREN PADICK
Roof/Waste drainage to street Cleared 8/11/2021 ABDULLAH SADOZAI
Tract Map conditions Cleared 8/11/2021 LAUREN PADICK
Hydrant and Access approval Cleared 1/14/2022 RUEL COLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/25/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 2/3/2022 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 2/23/2022 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 2/23/2022 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Partial Approval DAVID SCANTLIN
Green Building Rough 2/23/2022 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 2/23/2022 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 2/28/2022 Partial Approval DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 2/28/2022 Approved DAVID SCANTLIN
Green Building Rough 3/4/2022 Approved DAVID SCANTLIN
Insulation 3/4/2022 Approved DAVID SCANTLIN
Drywall Nailing 3/9/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 5/23/2022 Approved CHRIS CHRISTENSEN
Final 5/23/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/23/2022 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 5/23/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/27/2022 Approved CHRIS CHRISTENSEN
Final 5/27/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 5/27/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 5/27/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 5/27/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/27/2022 SGSOV Approved CHRIS CHRISTENSEN