423 S ROSSMORE AVE 90020
Certificate Information: 423 S ROSSMORE AVE 90020
- Application / Permit
- 20014-20000-03706
- Plan Check / Job No.
- B20VN11287
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT REC. ROOM TO ACCESSORY DWELLING UNIT W/2ND FLR ADDITION per LAMC 12.22 A.33(c) and (d) FIRE SPRINKLER NFPA-13D
- Permit Issued
- Issued on 9/8/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 10/8/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 10/30/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 11/10/2020 | APPLICANT |
| Plan Check Approved | 7/8/2021 | MOHAMMAD ESMAILI |
| Issued | 9/8/2021 | APPLICANT |
| CofO in Progress | 11/7/2023 | RICHARD DOCKUS |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
| CofO Issued | 11/26/2023 | DEROLD HAUFF |
| Permit Finaled | 11/26/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/8/2021 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 1/12/2021 | ELAINE LEI |
| Sewer availability | Cleared | 1/12/2021 | ELAINE LEI |
| Low Impact Development | Cleared | 1/15/2021 | MITESH PATEL |
| HPOZ | Cleared | 1/22/2021 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 1/22/2021 | SUKI GERSHENHORN |
| Miscellaneous | Cleared | 1/22/2021 | SUKI GERSHENHORN |
| ZI | Cleared | 1/22/2021 | SUKI GERSHENHORN |
| Roof/Waste drainage to street | Cleared | 1/28/2021 | RENZ SORIANO |
| Hydrant and Access approval | Cleared | 2/23/2021 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 3/1/2021 | RIDWAN HARDY |
Contact Information
| Architect | Spock,, Karen Zindler- Shuler; Lic. No.: C25136 | 1127 N LA BREA AVENUE INGLEWOOD, CA 90302 |
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/19/2021 | Approved | ARTHUR SARGSYAN |
| METHANE-Barrier | 11/19/2021 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 11/19/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2021 | Partial Approval | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2021 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 1/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Underground Mechanical | 1/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 2/24/2022 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 3/23/2022 | Approved | ARTHUR SARGSYAN |
| Insulation | 4/29/2022 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 4/29/2022 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 6/9/2022 | No Access for Inspection | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/13/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Interior/Exterior Lathing | 6/16/2022 | Approved | ADAM ESCOTO |
| Final | 5/24/2023 | Corrections Issued | RICHARD DOCKUS |
| Underground Mechanical | 6/15/2023 | Approved | LILIANA PORTILLO |
| Final | 6/29/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 6/29/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 6/29/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 6/29/2023 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Final | 7/17/2023 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Final | 7/17/2023 | Approved | JEFFREY MEAD |
| Smoke Detectors | 7/17/2023 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| HVAC-Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| PLUMBING-Final | 7/27/2023 | Not Ready for Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 8/30/2023 | Approved | ROY SPAULDING |
| Final | 8/30/2023 | Corrections Issued | ROY SPAULDING |
| HVAC-Final | 8/30/2023 | Approved | ROY SPAULDING |
| PLUMBING-Final | 8/30/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 11/6/2023 | Approved | RICHARD DOCKUS |
| Final | 11/6/2023 | OK to Issue CofO | RICHARD DOCKUS |
| HVAC-Final | 11/6/2023 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 11/6/2023 | Approved | RICHARD DOCKUS |