423 S ROSSMORE AVE 90020

Certificate Information: 423 S ROSSMORE AVE 90020

Application / Permit
20014-20000-03706
Plan Check / Job No.
B20VN11287
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT REC. ROOM TO ACCESSORY DWELLING UNIT W/2ND FLR ADDITION per LAMC 12.22 A.33(c) and (d) FIRE SPRINKLER NFPA-13D
Permit Issued
Issued on 9/8/2021
Issuing Office
Valley
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 MOHAMMAD ESMAILI
Corrections Issued 10/8/2020 MOHAMMAD ESMAILI
Quality Review Completed 10/30/2020 OMID HEDAYAT
Building Plans Picked Up 11/10/2020 APPLICANT
Plan Check Approved 7/8/2021 MOHAMMAD ESMAILI
Issued 9/8/2021 APPLICANT
CofO in Progress 11/7/2023 RICHARD DOCKUS
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/8/2021 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 1/12/2021 ELAINE LEI
Sewer availability Cleared 1/12/2021 ELAINE LEI
Low Impact Development Cleared 1/15/2021 MITESH PATEL
HPOZ Cleared 1/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 1/22/2021 SUKI GERSHENHORN
Miscellaneous Cleared 1/22/2021 SUKI GERSHENHORN
ZI Cleared 1/22/2021 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 1/28/2021 RENZ SORIANO
Hydrant and Access approval Cleared 2/23/2021 JOHN CONNEALLY
Construction near power lines Cleared 3/1/2021 RIDWAN HARDY

Contact Information

Architect Spock,, Karen Zindler- Shuler; Lic. No.: C25136 1127 N LA BREA AVENUE      INGLEWOOD, CA 90302
Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2021 Approved ARTHUR SARGSYAN
METHANE-Barrier 11/19/2021 Approved ARTHUR SARGSYAN
METHANE-Subgrade 11/19/2021 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/22/2021 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/27/2021 Partial Approval STUART CHAPMAN
PLUMBING-Rough 1/3/2022 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 1/3/2022 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 2/24/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 2/24/2022 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2022 Approved ARTHUR SARGSYAN
Green Building Rough 2/24/2022 Approved ARTHUR SARGSYAN
HVAC-Rough 2/24/2022 Approved ARTHUR SARGSYAN
METHANE-Rough 2/24/2022 Approved ARTHUR SARGSYAN
PLUMBING-Rough 2/24/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 3/23/2022 Approved ARTHUR SARGSYAN
Insulation 4/29/2022 Approved ARTHUR SARGSYAN
Shower Pan 4/29/2022 Approved ARTHUR SARGSYAN
Drywall Nailing 5/11/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 5/11/2022 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 6/9/2022 No Access for Inspection ADAM ESCOTO
Interior/Exterior Lathing 6/13/2022 Not Ready for Inspection ADAM ESCOTO
Interior/Exterior Lathing 6/16/2022 Approved ADAM ESCOTO
Final 5/24/2023 Corrections Issued RICHARD DOCKUS
Underground Mechanical 6/15/2023 Approved LILIANA PORTILLO
Final 6/29/2023 Not Ready for Inspection RICHARD DOCKUS
Green Building Final 6/29/2023 Approved RICHARD DOCKUS
PLUMBING-Final 6/29/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 6/29/2023 Corrections Issued RICHARD DOCKUS
HVAC-Final 7/17/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Final 7/17/2023 Approved JEFFREY MEAD
Smoke Detectors 7/17/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 7/27/2023 Not Ready for Inspection SCOTT FINNILA
Final 7/27/2023 Not Ready for Inspection SCOTT FINNILA
HVAC-Final 7/27/2023 Not Ready for Inspection SCOTT FINNILA
PLUMBING-Final 7/27/2023 Not Ready for Inspection SCOTT FINNILA
ELECTRICAL-Final 8/30/2023 Approved ROY SPAULDING
Final 8/30/2023 Corrections Issued ROY SPAULDING
HVAC-Final 8/30/2023 Approved ROY SPAULDING
PLUMBING-Final 8/30/2023 Approved ROY SPAULDING
ELECTRICAL-Final 11/6/2023 Approved RICHARD DOCKUS
Final 11/6/2023 OK to Issue CofO RICHARD DOCKUS
HVAC-Final 11/6/2023 Approved RICHARD DOCKUS
PLUMBING-Final 11/6/2023 Approved RICHARD DOCKUS