9447 HAINES CANYON AVE 91042
Certificate Information: 9447 HAINES CANYON AVE 91042
- Application / Permit
- 20014-20000-03701
- Plan Check / Job No.
- B20VN11266
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION TO (E) SFD, NEW ATT. 2-CAR GARAGE, NEW COVERED PATIO
- Permit Issued
- Issued on 7/1/2021
- Issuing Office
- Current Status
- CofO Issued on 10/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | CHON CHIO KUO |
| Corrections Issued | 9/8/2020 | CHON CHIO KUO |
| Quality Review Completed | 9/11/2020 | STEVEN KIM |
| Building Plans Picked Up | 9/11/2020 | APPLICANT |
| Applicant returned to address corrections | 12/2/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 5/25/2021 | CHON CHIO KUO |
| Plan Check Approved | 6/21/2021 | CHON CHIO KUO |
| Issued | 7/1/2021 | APPLICANT |
| CofO in Progress | 8/18/2022 | DAVID ANDERSON |
| CofO Issued | 10/22/2022 | MICHAEL SMITH |
| Permit Finaled | 10/22/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| ZA Case | Cleared | 9/11/2020 | STEVEN WECHSLER |
| Specific Plan | Cleared | 10/14/2020 | PEGGY MALONE-BROWN |
| BHO/Hillside ordinance | Cleared | 11/20/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/20/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/20/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/20/2020 | LEE GUILBEAUX |
| BHO/Hillside ordinance | Cleared | 11/20/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2020 | LEE GUILBEAUX |
| Permit | Cleared | 11/20/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/20/2020 | LEE GUILBEAUX |
| Work Adjacent to Public Way | Cleared | 11/20/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/20/2020 | LEE GUILBEAUX |
| GPI Written Notices | Cleared | 12/3/2020 | CHON CHIO KUO |
| Grading Pre-Inspection | Cleared | 12/3/2020 | CHON CHIO KUO |
| Hydrant and Access approval | Cleared | 12/18/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 6/10/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/10/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2021 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 7/28/2021 | Partial Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 8/12/2021 | Partial Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 8/12/2021 | Partial Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 8/24/2021 | Approved | WILLIAM KUEHN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Partial Inspection | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 10/18/2021 | Approved | WILLIAM KUEHN |
| ELECTRICAL-Rough | 10/18/2021 | Approved | WILLIAM KUEHN |
| Green Building Rough | 10/18/2021 | Not Ready for Inspection | WILLIAM KUEHN |
| HVAC-Rough | 10/18/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Rough | 10/18/2021 | Approved | WILLIAM KUEHN |
| Verify Sprinkler Sign Off | 10/18/2021 | Approved | WILLIAM KUEHN |
| Insulation | 12/3/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/3/2021 | Partial Inspection | WILLIAM KUEHN |
| Drywall Nailing | 12/13/2021 | Approved | WILLIAM KUEHN |
| Interior/Exterior Lathing | 12/15/2021 | Partial Inspection | WILLIAM KUEHN |
| Shower Pan | 12/15/2021 | Approved | WILLIAM KUEHN |
| PLUMBING-Final | 7/18/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/29/2022 | Approved | DAVID ANDERSON |
| Final | 7/29/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 7/29/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Rough | 7/29/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 7/29/2022 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 7/29/2022 | Corrections Issued | DAVID ANDERSON |
| Final | 8/17/2022 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 8/17/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 8/17/2022 | Approved | DAVID ANDERSON |
| Special/Order Compliance | 8/17/2022 | Approved | DAVID MATSON |
| Service/Power Release | 8/18/2022 | Approved | DAVID ANDERSON |