358 N BRONSON AVE 90004

Certificate Information: 358 N BRONSON AVE 90004

Application / Permit
20014-20000-03697
Plan Check / Job No.
B20VN11252
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (12'-3"x 11'-9') NEW MASTER BEDROOM AND (5'-7"x 11'-9") WALK IN CLOSET & INT REMODEL @ REAR PORTION OF (E) SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 10/29/2020
Issuing Office
Current Status
CofO Issued on 7/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 RICARDO RAMIREZ
Corrections Issued 9/5/2020 RICARDO RAMIREZ
Plan Check Approved 10/26/2020 TROY DEGUZMAN
Issued 10/29/2020 APPLICANT
CofO in Progress 7/16/2021 CHRIS CHRISTENSEN
Permit Finaled 7/21/2021 DEROLD HAUFF
CofO Issued 7/21/2021 DEROLD HAUFF
Permit Finaled 7/21/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/5/2020 JUAN ASHTON
Roof/Waste drainage to street Cleared 10/15/2020 JUAN ASHTON
Sewer availability Cleared 10/15/2020 JUAN ASHTON

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: C83911 121 N VAIL AVE      MONTEBELLO, CA 90640

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/17/2020 Corrections Issued DAVID FEILER
Deputy Drilled-In Anchors 12/18/2020 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 12/19/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 12/28/2020 Partial Approval CHRIS CHRISTENSEN
Wood Frame 1/26/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Rough 1/27/2021 Partial Approval CHRIS CHRISTENSEN
Deputy Wood Construction 1/29/2021 No Access for Inspection ELMER BLAND
Special/Order Compliance 2/3/2021 Corrections Issued STUART CHAPMAN
Special/Order Compliance 2/4/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/11/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/11/2021 Corrections Issued CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 3/11/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/18/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/18/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 3/18/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 3/18/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/18/2021 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 3/26/2021 Approved CHRIS CHRISTENSEN
Insulation 3/26/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 4/5/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 4/5/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/8/2021 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 5/28/2021 Approved CHRIS CHRISTENSEN
Final 5/28/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 5/28/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/28/2021 SGSOV Approved CHRIS CHRISTENSEN
Service/Power Release 5/28/2021 Approved CHRIS CHRISTENSEN
Smoke Detectors 5/28/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 6/4/2021 Approved CHRIS CHRISTENSEN
Final 6/4/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 6/4/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 6/4/2021 Approved CHRIS CHRISTENSEN
Final 7/15/2021 OK to Issue CofO CHRIS CHRISTENSEN
PLUMBING-Final 7/15/2021 Approved CHRIS CHRISTENSEN