16017 W JEANNE LANE 91436

Certificate Information: 16017 W JEANNE LANE 91436

Application / Permit
20014-20000-03694
Plan Check / Job No.
B20VN11244
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
6' 3" X 18' 8" ADDITION & DECK EXTENSION TO REAR. ALL WORK DONE PER STRUCTURAL ENGINERING.
Permit Issued
Issued on 11/25/2020
Issuing Office
Current Status
CofO Issued on 6/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2020 APPLICANT
Assigned to Plan Check Engineer 9/21/2020 GURUNATH NESARAJAH
Corrections Issued 9/22/2020 GURUNATH NESARAJAH
Building Plans Picked Up 9/23/2020 APPLICANT
Applicant returned to address corrections 10/14/2020 GURUNATH NESARAJAH
Plan Check Approved 11/10/2020 GURUNATH NESARAJAH
Issued 11/25/2020 APPLICANT
CofO in Progress 5/1/2021 MICHAEL PELHAM
Permit Finaled 6/1/2021 MICHAEL SMITH
CofO Issued 6/1/2021 MICHAEL SMITH
Permit Finaled 6/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/14/2020 BRIAN MILLER
Specific Plan Cleared 10/15/2020 TRACY WILLIAMS
Specific Plan Cleared 10/15/2020 TRACY WILLIAMS
Roof/Waste drainage to street Cleared 10/20/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/21/2020 JOHN TRIANTAFYLLOS
ZA Case Cleared 11/5/2020 PABLO ESTRADA
ZA Case Cleared 11/5/2020 PABLO ESTRADA

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/7/2020 Corrections Issued RONALD COWAN
Piling/Pier/Caisson 12/10/2020 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 1/20/2021 Approved RONALD COWAN
ELECTRICAL-Rough 1/20/2021 Approved RONALD COWAN
Green Building Rough 1/20/2021 Approved RONALD COWAN
PLUMBING-Rough 1/20/2021 Approved RONALD COWAN
Pre-Inspection 1/20/2021 Approved RONALD COWAN
Rough-Elec/Plmb/HVAC 1/20/2021 Approved RONALD COWAN
Drywall Nailing 1/25/2021 Approved DAVID SCANTLIN
Special/Order Compliance 2/3/2021 Approved RONALD COWAN
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Not Ready RONALD COWAN
Final 3/23/2021 Corrections Issued RONALD COWAN
Final 5/1/2021 OK to Issue CofO MICHAEL PELHAM
Footing/Foundation/Slab 5/1/2021 Approved MICHAEL PELHAM
Green Building Final 5/1/2021 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 5/1/2021 SGSOV Approved MICHAEL PELHAM
Smoke Detectors 5/1/2021 Approved MICHAEL PELHAM